InfraCompute / Deals
CyrusOne Data Centers Issuer I 2025-1
Data centre ABS for CyrusOne, US$575m, 24 January 2025.
Key terms
- Borrower or issuer
- CyrusOne
- Date
- 24 January 2025
- Structure
- Data centre ABS
- Amount
- US$575m
- Pricing
- 5.91%Class coupons from SEC Form N-PORT fund holding reports
- Tenor
- 5-yr ARD; 25-yr legal final
Recorded terms
- Lender type
- Bonds and securitisationsStructure: securitisation
- Tenor
- 5-yr ARD; 25-yr legal final
- Security
- 13 DCs in Northern Virginia, San Antonio and Houston
- Lenders and arrangers
- MUFG, KKR Capital Markets (arrangers); KeyBank (servicer); Structuring agent: MUFG Securities Americas Inc.; Banks named in accountants report (initial purchasers / arrangers): KKR Capital Markets LLC, SG Americas, Securities, LLC, Goldman Sachs & Co. LLC, Morgan Stanley & Co. LLC, SMBC Nikko Securities America, Inc., Santander US Capital Markets LLC, Citigroup Global Markets Inc., Natixis Securities Americas, BBVA Securities Inc., Intesa Sanpaolo IMI Securities Corp., Bank of China Limited, Desjardins Securities Inc., Loop Capital Markets LLC
- Trustee
- Citibank
- Tenant or offtaker
- 98 tenants, 83.5% IG; WA original lease term 8.6 yrs
Parties
Similar financings
Same structure, other borrowers, closest in date.
More from CyrusOne
Filed documents and legal terms
The documents behind this financing that are filed on SEC EDGAR, with the governing law each states. Read any document in full before relying on it; filers may redact commercial terms.
- Filed documents
- 1
- Governing law
- Not stated in the filed text
- Quoted in the clause and contract libraries
- 0
| Filed document | Dated | Governing law | In InfraCompute |
|---|---|---|---|
| Form ABS-15G Ex 99.1 (agreed-upon procedures / due diligence report) | 24 January 2025 | – | – |
In-house counsel working on similar terms? Ask Randeep for a market check or see what is market.
For counsel on this deal
Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.
Sources
- CyrusOne Data Centers Issuer I 2025-1Source date: 24 January 2025
About this record
Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.