Teraco: Historical growth and refinancing syndication

Corporate credit for Teraco, 31 January 2023.

Key terms

Borrower or issuer
Teraco
Date
31 January 2023
Structure
Corporate credit
Amount
ZAR11.8bn
Pricing
Not disclosed
Maturity
December 2028

Recorded terms

Lender type
Bank loansNo funder named; bank arranger: Absa (arranger)
Maturity
December 2028
Amount m · earlier observation
11800As of 31 January 2023

Indexed primary passage only: ZAR5.7bn growth plus6.1bn refinancing. Later facilities may overlap; no incremental market total.

Event date · earlier observation
31 January 2023As of 31 January 2023

Indexed primary passage only: ZAR5.7bn growth plus6.1bn refinancing. Later facilities may overlap; no incremental market total.

Maturity · earlier observation
December 2028As of 31 January 2023

Indexed primary passage only: ZAR5.7bn growth plus6.1bn refinancing. Later facilities may overlap; no incremental market total.

Growth component m
5700As of 31 January 2023

Full dated draws, repayments, fees, hedge costs and reserves remain unknown; no actual all-in cost eligibility. Overlap with later Teraco facilities remains unestablished.

Refinancing component m
6100As of 31 January 2023

Full dated draws, repayments, fees, hedge costs and reserves remain unknown; no actual all-in cost eligibility. Overlap with later Teraco facilities remains unestablished.

Maturity
December 2028As of 31 January 2023

Full dated draws, repayments, fees, hedge costs and reserves remain unknown; no actual all-in cost eligibility. Overlap with later Teraco facilities remains unestablished.

Parties

Related facilities

Similar financings

Same structure, other borrowers, closest in date.

More from Teraco

All Teraco financings →

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. Teraco R11.8bn syndicated financing releaseSource date: 31 January 2023

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.