Research profile
The register contains 5 financing and capital observations associated with Core Scientific, with recorded event dates from 2024-08-19 to 2026-08-27. The observations cover data centres. These records describe historical disclosures and may include amendments, packages and components of the same financing.
- Primary activities represented
- Data centres
- Business models in recorded context
- data centre operator
- Recorded currencies
- USD
- Named project connections
- 4
Core Scientific in the contract library
The filed financings Core Scientific sponsors or issues, with the lenders, size and terms of each.
Financing history
Connected developments and programmes
Named counterparties
Selected sources
- Core Scientific 3.00% convertible senior notes due 2029Source date: 19 August 2024
- Core Scientific 0.00% convertible senior notes due 2031Source date: 5 December 2024
- Core Scientific 364-day senior secured loan facility (US$1bn)Source date: 6 March 2026
- Core Scientific3.3bn secured notes pricingSource date: 22 April 2026
- Core Scientific RCF and letter of credit facilitySource date: 27 August 2026
About this record
Compiled from the announcements and filings linked on each financing. Roles are as disclosed; a named arranger, agent or trustee may not hold the debt. Methodology · Send a correction.
Read the structure
Filed documents
5 documents behind these financings are filed on SEC EDGAR. Governing law across them: New York law (1).
| Deal | Filed document | Dated | Governing law | In InfraCompute |
|---|---|---|---|---|
| Core Scientific RCF and letter of credit facility | SEC Form 8-K (financing announcement / closing) | 27 August 2026 | – | – |
| Core Scientific CoreWeave-leased campuses HY project bond | Indenture, 7.75% Senior Secured Notes 2031 (Ex 4.1) + 8-K | 6 May 2026 | New York law | – |
| Core Scientific 364-day senior secured loan facility (US$1bn) | SEC Form 8-K (financing announcement / closing) | 6 March 2026 | – | – |
| Core Scientific 0.00% convertible senior notes due 2031 | SEC Form 8-K (financing announcement / closing) | 5 December 2024 | – | – |