Tools  /  Checklists  /  GPU delayed draw term loan: conditions precedent

Checklist · 43 items · 9 sections

GPU delayed draw term loan: conditions precedent

The documents and evidence lenders usually ask for before a GPU facility closes and before each draw. The filed facilities differ in what is a condition and what is a post-closing undertaking, so check each item against the term sheet.

For: Borrower and lender legal teams preparing for signing, first draw and each later draw of a GPU-backed delayed draw facility.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What it covers

Corporate and authority

  1. Constitutional documents and a structure chart for the borrower, its parent and any guarantor
  2. Board and, where needed, shareholder resolutions approving each finance document

3 more items in the PDF.

Free PDF

Get the full checklist

All 43 items as a PDF you can use in a transaction file.

Free. Work email only. The download starts here once the form is accepted. How we handle your details.

How to use it

A general starting list, not a complete list for any deal. Items that link to filed terms show how the public deals handle the point. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.