When does the hyperscaler have to choose, and what happens if it says nothing?
Google’s backstops of the Fluidstack leases turn on one trigger: Fluidstack’s insolvency, or a payment event of default under the lease. The landlord must tell Google at once. Google then has 30 days to verify the trigger and choose between letting the lease end against a termination fee and taking the lease over. Silence is not neutral. If Google says nothing, it is treated as rejecting the lease, unless only assumption is open, in which case it is treated as assuming it. At Barber Lake the test that decides whether rejection is open is applied phase by phase.
Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·
What the filed contracts say
Contract
What the filed wording says
Google recognition (TeraWulf)
The trigger is Fluidstack’s insolvency or a payment event of default. The landlord must notify Google immediately, and Google has 30 days to verify it.
Google recognition (TeraWulf)
If Google neither elects nor defers within the 30 days, it is deemed to reject the lease, or deemed to assume it where only assumption is open.
Google recognition (Cipher)
At Barber Lake the fit-out test is measured against an initial baseline for the phase I areas until phase II starts, then against a later baseline for the whole premises. Both figures are redacted.
The filed wording
In the event that (i) Fluidstack has become subject to an Insolvency Event or (ii) an Event of Default under Section 15.1.1 of the Fluidstack Lease has occurred (the occurrence of (i) or (ii), the “FS Default Trigger”), Akela will immediately provide Google written notice (the “Google Default Notice”) that the FS Default Trigger has occurred. An “Insolvency Event” is the occurrence of an event identified in Section 15.1.3 of the Fluidstack Lease. Thereupon, Google will have a period of 30 days after receipt of the Google Default Notice (“Verification Period”) to verify that the requirements of the FS Default Trigger have been met. … For the avoidance of doubt, if Google has neither provided the Google Election Notice or elected the Deferral Option by written notice on or before the end of the Verification Period, Google will be deemed to have elected the Google Rejection Option (or, in the case of the Assumption Only Condition, Google will be deemed to have elected the Google Assumption Option).
Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.