Macquarie lent Applied Digital money to buy land and start building before any lease was signed. The loans run for about two years, but fall due within months if the lease is not signed by a set date. The $100m note matures in December 2027, or in July 2026 if the lease is not signed by 18 April 2026. The project is defined by reference to an exclusivity agreement with a US investment grade hyperscaler. The earlier $50m note needed a 200 MW lease with a tenant rated at least BBB-, not an Applied Digital affiliate, by 31 October 2025.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What the filed contracts say

ContractWhat the filed wording says
Macquarie $100m development noteThe $100m note matures on 18 December 2027, but falls due on 18 July 2026 if the lease is not signed by 18 April 2026.
Macquarie $100m development noteThe project is a hyperscale campus for a US investment grade hyperscaler that signed an exclusivity agreement with Applied Digital on 3 October 2025.
Macquarie $50m development noteThe $50m note fell due on 1 February 2026 unless a 200 MW lease was signed by 31 October 2025; otherwise it ran to 9 September 2027.
Macquarie $50m development noteThe lease had to be with a tenant rated at least BBB- that is not an Applied Digital affiliate.

The filed wording

(b) Maturity Date. All principal and accrued interest on the unpaid principal of this Note will be due and payable in immediately available funds upon the earliest of (i) the date of acceleration of the Loan hereunder, (ii) July 18, 2026, to the extent the Initial Lease Execution has not occurred on or before April 18, 2026, or (iii) December 18, 2027 (the “Maturity Date”).
Macquarie development loan to Applied Digital (APLD DevCo), $100m, for a hyperscale campus before the lease, section 2(b) · Applied Digital 8-K, Exhibit 10.1

On the deal pages

Financings by the parties to these contracts

The latest debt raised by the companies that signed them, with the terms and the sources on each deal page.

FinancingBorrower or issuerDateAmount
Applied Digital 7.00% senior secured notes due 2031Applied Digital16 June 2026US$1.59bn
RevolverApplied Digital29 May 2026US$350m
APLD ComputeCo 3 bridge construction facilityApplied Digital1 May 2026US$300m
Senior notesApplied Digital10 March 2026US$2.15bn
Senior secured notesApplied Digital20 November 2025US$2.35bn

Follow alerts

Follow The lease-signing deadline

New filed wording for this clause from customer contracts, leases, colocation, power contracts and backstops. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Method

Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.