How much will lenders advance against turbines or transformers before they are installed?

Fermi has two loans against equipment bought ahead of need. The turbine loan from MUFG advances 65% against delivered turbines and 55% against turbines still on order. Each figure applies to the lower of purchase cost and appraised orderly liquidation value, and for turbines on order the payments still owed to Siemens come off first. When equipment arrives and an independent auditor confirms it, the borrower can draw a one-time top-up. The high voltage equipment loan from Keystone advances 80% of the purchase price, with 20% equity from the borrower.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What the filed contracts say

ContractWhat the filed wording says
Fermi turbine warehouse loanThe advance rate is 65% for delivered equipment and 55% for equipment still on order.
Fermi turbine warehouse loanIt applies to the lower of purchase cost and appraised value; for turbines on order, the payments still due to the manufacturer are deducted.
Fermi turbine warehouse loanAppraised value for the Siemens equipment is its orderly liquidation value.
Fermi turbine warehouse loanOnce title passes and an independent auditor confirms delivery, the borrower may draw a one-time top-up.
Fermi turbine warehouse loanThe loan matures on 10 August 2027.
Fermi high voltage equipment loanFor high voltage equipment the advance rate is 80% of the purchase price, with the borrower funding the other 20% in cash.

The filed wording

“Debt Sizing Percentage (Delivered Equipment)” means 65%. “Debt Sizing Percentage (Undelivered Siemens Firebirds Equipment)” means 55%. “Debt Sizing Percentage (Undelivered Siemens F-Class Equipment)” means 55%
Fermi turbine warehouse equipment supply loan (Siemens and GE gas turbines), MUFG as agent, Exhibit A, “Debt Sizing Percentage” · Fermi 8-K, Exhibit 10.1

On the deal pages

Financings by the parties to these contracts

The latest debt raised by the companies that signed them, with the terms and the sources on each deal page.

FinancingBorrower or issuerDateAmount
Fermi 5.00% convertible senior notes due 2031Fermi Inc.15 July 2026US$375m

Follow alerts

Follow Lending against long-lead equipment

New filed wording for this clause from customer contracts, leases, colocation, power contracts and backstops. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Method

Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.