Tools  /  Contract library  /  Term, escalation and early termination of rented generation

Contract library · Power

Term, escalation and early termination of rented generation

Can the data centre get out of a turbine rental early, and what does it pay?

Each turbine is rented for a fixed term from go-live. The customer cannot cancel an order without the lessor’s approval. If it terminates early, other than for the lessor’s default, it pays a termination payment: a percentage of the remaining rent, with a higher percentage in the first three years. The parties agree that payment is a genuine pre-estimate of loss, not a penalty. Rent rises with CPI from the third year.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What the filed contracts say

ContractWhat the filed wording says
Solaris turbine rentalThe customer may cancel a rental order only with the lessor’s approval, in its sole discretion, and pays cancellation charges.
Solaris turbine rentalEarly termination by the customer, or after its default, costs a redacted percentage of the remaining rent, higher in the first three years of each turbine’s term.
Solaris turbine rentalThe parties agree the termination payment is a genuine pre-estimate of loss, not a penalty, recoverable as a debt.
Solaris turbine rentalRent escalates each year with CPI, starting in the third year of each turbine’s term.

The filed wording

Any Rental Order may be cancelled by Customer only upon approval by an authorized officer of Lessor, said approval to be in Lessor’s sole discretion.
Mobile Energy Rentals (Solaris)–CTC Property amended and restated master equipment rental agreement for behind-the-meter turbines, section 2 · Solaris Energy Infrastructure 10-Q, Exhibit 10.4

Follow alerts

Follow Term, escalation and early termination of rented generation

New filed wording for this clause from customer contracts, leases, colocation, power contracts and backstops. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Method

Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.