CleanSpark Sandersville (Meta) senior secured notes

Project bond for CleanSpark, US$2.28bn, 18 September 2026.

Key terms

Borrower or issuer
CleanSpark
Date
18 September 2026
Structure
Project bond
Amount
US$2.28bn
Pricing
7.875%
Tenor
Due 1 Oct 2031

Recorded terms

Lender type
Bonds and securitisationsStructure: notes or bonds
Tenor
Due 1 Oct 2031
Security
First-priority liens on issuer and CSRE Properties assets; CleanSpark completion guarantee; debt service reserve funded from proceeds
Lenders and arrangers
Morgan Stanley (representative of the initial purchasers)
Tenant or offtaker
Meta subsidiary (reported; 20-year NNN lease, 175MW)

Similar financings

Same structure, other borrowers, closest in date.

More from CleanSpark

All CleanSpark financings →

Filed documents and legal terms

The documents behind this financing that are filed on SEC EDGAR, with the governing law each states. Read any document in full before relying on it; filers may redact commercial terms.

Filed documents
1
Governing law
New York law
Quoted in the clause and contract libraries
0
(a) THIS INDENTURE, THE NOTES, AND THE SUBSIDIARY GUARANTEE SHALL BE GOVERNED BY, AND CONSTRUED IN ACCORDANCE WITH THE LAWS OF THE STATE OF NEW YORK.

From the 7.875% Senior Secured Notes due 2031 (EX-4.1), filed with the SEC.

Filed documentDatedGoverning lawIn InfraCompute
7.875% Senior Secured Notes due 2031 (EX-4.1)25 September 2026New York law–

In-house counsel working on similar terms? Ask Randeep for a market check or see what is market.

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. CleanSpark Sandersville (Meta) senior secured notesSource date: 18 September 2026

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.