EdgeConneX: Jakarta sustainability-linked senior facilities

Development credit for EdgeConneX, 13 September 2023.

Key terms

Borrower or issuer
EdgeConneX
Date
13 September 2023
Structure
Development credit
Amount
US$403.8m
Pricing
Not disclosed
Sources
1 public source below

Recorded terms

Lender type
Bank loansNamed lender: senior lenders and hedge banks
Event date
13 September 2023As of 13 September 2023

Historical package added for geographic breadth. Current outstanding amount, legal recourse, sustainability KPI mechanics and later refinancing not reviewed. EdgeConneX absent from inherited 94. Package is one disclosed financing event; do not add cumulative nearly5000m corporate fundraising headline. No complete borrower cash-flow schedule, issue price, fees, amortisation, hedging and benchmark observations available; exclude from all-in-cost ranking.

Instrument
sustainability-linked senior facilitiesAs of 13 September 2023

Historical package added for geographic breadth. Current outstanding amount, legal recourse, sustainability KPI mechanics and later refinancing not reviewed. EdgeConneX absent from inherited 94. Package is one disclosed financing event; do not add cumulative nearly5000m corporate fundraising headline. No complete borrower cash-flow schedule, issue price, fees, amortisation, hedging and benchmark observations available; exclude from all-in-cost ranking.

Parties

Project connections

Similar financings

Same structure, other borrowers, closest in date.

More from EdgeConneX

All EdgeConneX financings →

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. EdgeConneX Secures $403.8 Million in Sustainability-Linked Financing to Support Expansion in AsiaSource date: 13 September 2023

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.