Vantage Data Centers: North America green borrowing-base facility upsize

Corporate credit for Vantage Data Centers, 3 June 2025.

Key terms

Borrower or issuer
Vantage Data Centers
Date
3 June 2025
Structure
Corporate credit
Amount
US$5.75bn
Pricing
Not disclosed
Sources
1 public source below

Recorded terms

Lender type
Lender type not establishedNo lender named in the public sources held
Incremental amount m
2750As of 3 June 2025

Amendment is a facility-history event. 5750m total and 2750m increment must not be added. Supports development and land acquisitions; no specific site allocation. Amends 2024 3000m corporate facility, absent from inherited 94. Do not also record source headline 5000m as a separate facility; that headline combines this increment with New Albany. No complete borrower cash-flow schedule, issue price, fees, amortisation, hedging and benchmark observations available; exclude from all-in-cost ranking.

Event date
3 June 2025As of 3 June 2025

Amendment is a facility-history event. 5750m total and 2750m increment must not be added. Supports development and land acquisitions; no specific site allocation. Amends 2024 3000m corporate facility, absent from inherited 94. Do not also record source headline 5000m as a separate facility; that headline combines this increment with New Albany. No complete borrower cash-flow schedule, issue price, fees, amortisation, hedging and benchmark observations available; exclude from all-in-cost ranking.

Instrument
corporate borrowing-base credit facility amendmentAs of 3 June 2025

Amendment is a facility-history event. 5750m total and 2750m increment must not be added. Supports development and land acquisitions; no specific site allocation. Amends 2024 3000m corporate facility, absent from inherited 94. Do not also record source headline 5000m as a separate facility; that headline combines this increment with New Albany. No complete borrower cash-flow schedule, issue price, fees, amortisation, hedging and benchmark observations available; exclude from all-in-cost ranking.

Parties

Similar financings

Same structure, other borrowers, closest in date.

More from Vantage Data Centers

All Vantage Data Centers financings →

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. Vantage Data Centers Secures $5B in Incremental Green Loan Financings to Support Demand for North America PlatformSource date: 3 June 2025

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.