InfraCompute / Deals
Scala Data Centers Chile project financing
Green project finance for Scala Data Centers, US$254m green project finance, plus a VAT facility (US$328m in total), 18 July 2025.
Key terms
- Borrower or issuer
- Scala Data Centers
- Date
- 18 July 2025
- Structure
- Green project finance
- Amount
- US$254m green project finance, plus a VAT facility (US$328m in total)
- Pricing
- Not disclosed
- Sources
- 1 public source below
Recorded terms
- Lender type
- Bank loansNamed lender: MUFG
- Lenders and arrangers
- MUFG, SMBC, BNP Paribas and Natixis
- Use of proceeds
- Three hyperscale data centres (Curauma, Lampa, Huechuraba 2) and the Nova Lampa substation
- Region
- Chile
- Notes
- Scala's first international project financing, aligned with its Green Bond Framework. Described as the largest single data centre project financing in Latin America at the time.
Parties
Similar financings
Same structure, other borrowers, closest in date.
More from Scala Data Centers
For counsel on this deal
Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.
Sources
- InvestChile: Scala expands in ChileSource date: 2026
About this record
Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.