Project bond for TeraWulf, US$1.3bn, 29 December 2025.

Key terms

Borrower or issuer
TeraWulf
Date
29 December 2025
Structure
Project bond
Amount
US$1.3bn
Pricing
7.25%
Tenor
2030; installment amortisation (s.14.01)

What’s notable

A US$1.3bn high-yield project bond at 7.25% due 2030 for the Abernathy joint venture. Fluidstack is the tenant, and Google supports the lease through a financial support agreement and a lease recognition agreement. The security package includes a lockbox, mortgages and a US$75m ground lease letter of credit.

Recorded terms

Lender type
Bonds and securitisationsStructure: notes or bonds
Tenor
2030; installment amortisation (s.14.01)
Security
Equity of issuer and company parties; all assets; Fluidstack USA III lockbox; HoldCo account pledge pre-completion; warrants during construction; mortgages; US$75m ground lease LC
Lenders and arrangers
Agent: Wilmington Trust (collateral agent)
Trustee
Wilmington Trust (trustee/collateral agent); Wilmington Trust (trustee and collateral agent)
Tenant or offtaker
Fluidstack USA III Inc. (lease 26 Sep 2025) with Google Financial Support Agreement and Lease Recognition Agreement

Parties

Similar financings

Same structure, other borrowers, closest in date.

More from TeraWulf

All TeraWulf financings →

Filed documents and legal terms

The documents behind this financing that are filed on SEC EDGAR, with the governing law each states. Read any document in full before relying on it; filers may redact commercial terms.

Filed documents
2
Governing law
New York law
Quoted in the clause and contract libraries
1
THE INDENTURE, THIS NOTE AND THE SUBSIDIARY GUARANTEE SHALL BE GOVERNED BY AND CONSTRUED IN ACCORDANCE WITH THE LAWS OF THE STATE OF NEW YORK.

From the Indenture, 7.25% Senior Secured Notes 2030 (Ex 4.1), filed with the SEC.

In-house counsel working on similar terms? Ask Randeep for a market check or see what is market.

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. TeraWulf / Fluidstack Abernathy JV HY project bondSource date: 29 December 2025

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.