STACK Infrastructure: TKY01 green development facility

Development credit for STACK Infrastructure, 23 October 2025.

Key terms

Borrower or issuer
STACK Infrastructure
Date
23 October 2025
Structure
Development credit
Amount
JPY39.7bn
Pricing
Not disclosed
Sources
1 public source below

Recorded terms

Lender type
Bank loansNamed lender: Natixis CIB (underwriter and green loan coordinator)
Event date
23 October 2025As of 23 October 2025

Selected public disclosure only. Executed documents, current balances and complete borrower costs were not audited.

Parties

Project connections

Similar financings

Same structure, other borrowers, closest in date.

More from STACK Infrastructure

All STACK Infrastructure financings →

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. STACK TKY01 green development financingSource date: 23 October 2025

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a financing like this one? Book 20 minutes with Randeep to see how it compares.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.