Hyperscaler lease-backed project bonds
How a strong customer contract supports a project without guaranteeing its bonds.
A lease-backed project bond relies on cash owed under specified leases or service contracts and on the issuer's financing structure. A hyperscaler relationship can strengthen a payment stream without making that hyperscaler liable for every project obligation.
- 01Tenant obligation
- 02Project collections
- 03Reserves & costs
- 04Bond debt service
Trace the promise to its beneficiary
Begin with the legal tenant, any guarantor and the obligation covered by support. Rent, termination amounts, power charges and debt service are separate promises. Identify who may claim, when payment is due and the relevant cap. Avoid moving a guarantee across entities simply because it appears in the same project announcement.
Examine the delivery interface
Before acceptance, project completion and customer payment obligations may not align. Compare construction milestones, longstop dates, fit-out requirements and service tests with draw conditions. Determine who pays interest, operating costs and overrun amounts while customer billing has not begun. A long lease term does not fund a delayed start by itself.
Match contractual cash to the bond schedule
Model lease collections against bond principal, interest, reserves and essential operating costs by period. Separate indexation and power pass-through from fixed rent. Examine expiry, renewal and termination assumptions. A contracted revenue total is not cash available for debt service and should not be used as a simple coverage multiple.
Read a disclosed example narrowly
The River Bend filing separates lease-related support from the project notes and states that the notes are not guaranteed by the parent, tenant or lease guarantor. The existing interactive credit-support case maps that distinction. The lesson is to follow the obligation and beneficiary, rather than infer noteholder recourse from a recognisable corporate name.
when a landlord builds an AI data centre campus for a neocloud or hyperscaler, it often refinances construction with a secured bond issued by the campus-owning company. Investors buy the lease, so the coupon tracks the tenant's credit. Public deals in 2025 and 2026 show a clear pricing ladder, from about 9.25% for a non-investment-grade tenant to under 7% for an investment-grade one.
The structure
- Issuer. A ring-fenced company owns the campus, its leases and its accounts.
- Leases. Typically triple-net, 10 to 15 years, with one tenant or a small group.
- Security. Land, buildings, equipment, the leases, accounts and the shares in the issuer.
- Construction support. The sponsor gives a completion guarantee until the buildings are delivered and rent starts.
- Reserves. A debt service reserve funded at closing, sometimes sized to cover interest during construction.
- Cash management. A waterfall, with sweeps or scheduled amortisation.
- Offering. Usually Rule 144A, high yield or investment grade depending on the tenant.
The pricing ladder: 2025-26 public deals
| Issuer (campus) | Date | Size | Coupon | Tenant / credit support |
|---|---|---|---|---|
| Applied Digital (Polaris Forge 1) | Nov 2025 | US$2.35bn | 9.25% at 97.0 | CoreWeave |
| Core Scientific (CoreWeave campuses) | May 2026 | US$3.3bn | 7.75% at 99.25 | CoreWeave |
| TeraWulf (Lake Mariner) | Oct 2025 | US$3.2bn | 7.75% | Fluidstack, Google backstop |
| TeraWulf / Fluidstack JV (Flash Compute) | Dec 2025 | US$1.3bn | 7.25% | Fluidstack, Google backstop |
| Cipher (Barber Lake) | Nov 2025 | US$1.4bn | 7.125% | Fluidstack, Google backstop |
| Applied Digital (Polaris Forge 3, ELN-04) | Jun 2026 | US$1.59bn | 7.00% | Hyperscaler-grade tenant |
| Applied Digital (Polaris Forge 2) | Mar 2026 | US$2.15bn | 6.75% | Oracle (BBB) |
| Hut 8 (River Bend) | Apr 2026 | US$3.25bn | Investment grade (coupon n/d) | Fluidstack, Google backstop; c. 16.5-year amortising |
| Meta Hyperion (Beignet Investor) | Oct 2025 | US$27.3bn | c. T + 225bp, S&P A+ (prelim.) | Meta leases plus residual value guarantee |
Source: issuer indentures and filings listed below; Meta pricing from public reporting. Sizes are at issue.
Three patterns are visible:
- Tenant credit drives price. The same sponsor, Applied Digital, priced at 9.25% with CoreWeave as tenant and 6.75% with Oracle.
- Backstops narrow the gap. Google-backstopped Fluidstack leases priced between the CoreWeave and Oracle deals.
- Longer, amortising debt needs investment-grade support. Hut 8 and Meta Hyperion, with the strongest credit support, raised long-dated amortising debt; the high-yield deals are around five years.
Key terms in the indentures
Cash sweeps and amortisation. The Google-backstopped bonds (TeraWulf, Cipher, Flash Compute) sweep 50% of excess cash flow. Core Scientific's notes repay in instalments of 11.5% a year of original principal.
Lease termination redemption. If a tenant pays a termination fee, bondholders expect it to repay the notes. Applied Digital's Polaris Forge 2 indenture includes a "Datacenter Lease Termination Fee Mandatory Redemption".
Add-on debt. Indentures allow more notes for new buildings, subject to limits. Flash Compute caps add-on debt at 70% loan-to-cost; Core Scientific at 85%.
Reserves. Debt service reserves are large at closing because there is no rent yet. TeraWulf's indenture sets the required amount at US$447m on the issue date, then, during construction, US$265m plus the next two scheduled interest payments, less interest already paid. Cipher's deal follows a similar pattern (US$210m at issue, US$110m base amount).
Completion support. Every high-yield deal in the table relies on sponsor completion guarantees until rent starts, because investors are funding buildings that are not yet built.
How this compares with other options
| Lease-backed project bond | Construction loan | Data centre ABS | |
|---|---|---|---|
| Stage | Construction to early operation | Construction | Stabilised |
| Investors | Bond market (HY or IG) | Banks | ABS investors |
| Rate | Fixed | Floating | Mostly fixed |
| Typical term | About 5 years (HY); longer if IG | 2 to 3 years | ARD about 5 years |
| Tenant base | One or a few tenants | One or a few | Diversified pool |
Questions to take to the documents
- Does support cover rent, completion, residual value or debt service?
- Which delivery failures permit termination or suspend payment?
- What happens to the debt if the lease ends before final maturity?
Explore the disclosed examples
Open a register record for its dated amount, classification and source limitations. A link is not certification of all terms.
Questions clients ask
- What is a lease-backed project bond?
- A secured bond issued by a ring-fenced company that owns a data centre campus, repaid from rent under leases to one or a few tenants. Investors look mainly to the lease and the tenant's credit.
- Why do these bonds price so differently?
- Because pricing follows the tenant. In 2025-26 public deals, campuses leased to non-investment-grade neoclouds priced around 7.75% to 9.25%, while those with an investment-grade tenant or a Google backstop priced around 6.75% to 7.25%.
- What protects bondholders during construction?
- Completion guarantees from the sponsor, debt service reserves funded at closing and, in some deals, limits on additional debt measured by loan-to-cost.
For in-house counsel
Take it to the documents
The filed wording behind this piece, for the lender’s or the borrower’s side. Previews are open; the full text is free with InfraCompute Weekly.
- Bond protectionsCovenants and holder protections in data centre and neocloud bonds, from the indentures.
- Financing clause libraryCash traps, coverage ratios, cures, step-in and GPU security, quoted from credit agreements and indentures.
- Issues list: Bond indentureBuild it from the lender’s or the borrower’s side, with where filed deals land.
- The legal desk for in-house counselContract library, issues lists, checklists and English law notes.
Sources for the examples
Selected public sources support the examples. The analytical framework is InfraCompute editorial work; source links do not imply a complete agreement or legal review.
- Hut 8 Q2 2026 Form 10-Q — River Bend notes ↗Disclosure date: 2026-08-04
- Applied Digital Polaris Forge 1 9.25% notes indenture (Ex 4.1) ↗
- Applied Digital Polaris Forge 2 6.75% notes indenture (Ex 4.1) ↗
- TeraWulf Lake Mariner 7.75% notes indenture (Ex 4.1) ↗
- Cipher Barber Lake 7.125% notes indenture (Ex 4.1) ↗
- Core Scientific 7.75% notes indenture (Ex 4.1) ↗
- Hut 8 Q1 2026 results (Ex 99.1) ↗