Facility histories

How much is actually additional?

Separate the previous commitment, the increase and the resulting facility. Keep the amendment attached to its history.

Vantage / DataBank · commitment historiesSelected dated disclosures
Vantage / DataBank · commitment histories
SELECT A PATH TO FOLLOW THE EVIDENCE
How to read this case

Keep the basis in view.

Vantage’s corporate facility increased from $3bn to $5.75bn. The $2.75bn increment is distinct from the separate $2.25bn construction financing in the same announcement. DataBank increased its facility from $725m to $1.6bn; the $875m increment is arithmetic.

These are dated commitment capacities, not drawn balances or current availability. Do not add a resulting commitment to its own increment. Site-level allocations and subsequent facility changes require their own evidence.

Continue exploring / 04One package. Different rate exposures.
Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a GPU or data centre financing? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.