| Nscale / Microsoft SOW | The service term of each tranche begins on acceptance. Microsoft has 35 days to test the first tranche (and the first after a technology change) and 5 days for the rest. |
| IREN / Microsoft SOW | Silence is acceptance: no rejection notice within the acceptance period means the tranche is accepted. |
| Sharon AI MSA | Two weeks of testing against criteria agreed before go-live, unless the service order says otherwise. |
| CoreWeave / Microsoft MSA | Fees are payable after Microsoft accepts the services and receives a proper invoice. |
| Boost Run–Cohere service agreement | The customer has seven business days from the ready-for-testing notice and the NVIDIA validation report to test each rack. |
| Boost Run–Cohere service agreement | Silence or placing a production workload on a rack is deemed acceptance. |
| Boost Run–Cohere service agreement | Fees for a rack start on acceptance, and late acceptance extends the term day for day. |
| Anthropic / Nscale GPU order | Anthropic tests each delivered tranche against written acceptance criteria and must give reasons, with evidence, for rejecting it. |
| Anthropic / Nscale GPU order | Silence through the acceptance period is deemed acceptance. |
| Anthropic / Nscale GPU order | No payment starts until the whole tranche is accepted and fully available. |