Contract library · Data centre construction

Substantial completion, retainage and lien waivers

When is the building done, and what does the owner hold back until it is?

The owner holds back 10% of each payment until substantial completion. Half is released at substantial and final completion; the other half 30 days after the defect correction period ends. The Ward County form of parent guarantee is marked not used, so the retainage is the main security. Substantial completion needs every system working, the building ready for full commercial operation, permits, warranties assigned, any delay damages paid and lien waivers from the contractor and every subcontractor.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What the filed contracts say

ContractWhat the filed wording says
Nscale Ward County design-buildRetainage is 10% of each payment until substantial completion; half is released at substantial and final completion, the rest 30 days after the defect period.
Nscale Ward County design-buildThe form of parent guarantee is marked as not used.
Nscale Ward County design-buildSubstantial completion needs the facility ready for full commercial operation, with any delay damages paid and lien waivers from the contractor and all subcontractors.

The filed wording

§ 1.4.20 Retainage. “Retainage” means the amount equal to ten percent (10%) of each payment for the Work performed up to the achievement of Substantial Completion, fifty percent (50%) of which shall be released at Substantial Completion and Final Completion in accordance with Sections 9.8.5 and 9.10.2 and the remaining fifty percent (50%) shall be released thirty (30) days following the expiry of the Defect Correction Period.
Nscale Ward County data centre design-build agreement (AIA A141, four buildings near Odessa, Texas), section 1.4.20 · KiNRG S-1/A, Exhibit 10.13

On the deal pages

Financings by the parties to these contracts

The latest debt raised by the companies that signed them, with the terms and the sources on each deal page.

FinancingBorrower or issuerDateAmount
Pre-IPO convertible loan-note subscription (initial minimum)Nscale15 September 2026US$2.1bn
Dell short-term equipment lease payment schedules (aggregate)Nscale4 September 2026US$2.54bn
North Carolina GPU DDTLNscale31 August 2026US$1.2bn
Ward County GPU DDTLNscale31 August 2026US$1.85bn
Macquarie Iceland GPU facilityNscale29 July 2026US$331.9m

Follow alerts

Follow Substantial completion, retainage and lien waivers

New filed wording for this clause from customer contracts, leases, colocation, power contracts and backstops. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Method

Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.