What delivery commitment does a server maker give for a GPU order, and what excuses a delay?

Dell’s standard terms say delivery dates are indicative. For IREN’s GB300 order Dell went further, but only to commercially reasonable efforts: it will try to deliver the racks in four phases, each with a final shipment date. Delay is excused for force majeure, industry-wide component shortages, delays caused by the buyer and the buyer’s late payment, among others. If a phase runs late by more than an agreed number of business days, Dell must say so in writing and say whether an excused event caused it. The buyer can swap the servers in phases 3 and 4 for another product on at least four months’ notice, by cancelling that part of the order and placing a new one of equal or greater value. For lenders and customers: the supplier’s date is not a firm date, so the customer contract needs its own delay allowance.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

What the filed contracts say

ContractWhat the filed wording says
Dell–IREN purchase agreementUnder Dell’s standard terms, delivery dates are indicative.
Dell–IREN GB300 order termsFor this order, Dell uses commercially reasonable efforts to deliver each of four phases by its final shipment date.
Dell–IREN GB300 order termsDelay is excused for force majeure, industry-wide component shortages, buyer delays and late payment.
Dell–IREN GB300 order termsIf a phase is late beyond an agreed period, Dell must give notice and say whether an excused event caused it.
Dell–IREN GB300 order termsPhases 3 and 4 can be swapped for another product on at least four months’ notice, with a new order of equal or greater value.

The filed wording

3.1 Shipment. Unless otherwise agreed, Supplier shall arrange for shipment of the ordered Products to the ship-to address indicated in the Order, through a common carrier designated by Supplier. Delivery dates are indicative.
Dell purchase agreement with IREN’s Hardware 3 subsidiary (GPU servers), amending Dell’s Commercial Terms of Sale, Commercial Terms of Sale, clause 3.1 · IREN 10-Q, Exhibit 10.4

On the deal pages

Financings by the parties to these contracts

The latest debt raised by the companies that signed them, with the terms and the sources on each deal page.

FinancingBorrower or issuerDateAmount
Mackenzie GPU financing (reported)IREN27 August 2026US$2.4bn
Microsoft DDTL floating trancheIREN1 June 2026US$1.55bn
Microsoft US private-placement notesIREN1 June 2026US$2.1bn
Convertible notesIREN14 May 2026US$3bn
IREN US$2.3bn convertible notes due 2032 and 2033 (December 2025)IREN8 December 2025US$2.3bn

Follow alerts

Follow Delivery by phase, and the delays the supplier is excused for

New filed wording for this clause from customer contracts, leases, colocation, power contracts and backstops. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Method

Each extract is quoted from the contract as filed with the SEC, checked against the filed text when it was added; “…” marks words left out. Filers redact commercial terms, so a [***] or [*] is the filer's, not ours. The summaries describe the wording, not how a court would read it, and each contract's defined terms and other clauses can change the effect. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.