InfraCompute / Deals
IREN: Microsoft US private-placement notes
GPU secured for IREN, 1 June 2026.
Key terms
- Borrower or issuer
- IREN
- Date
- 1 June 2026
- Structure
- GPU secured
- Amount
- US$2.1bn
- Pricing
- 5.96% nominal coupon
- Maturity
- 31 December 2031 or earlier on final contract fee payment
Recorded terms
- Lender type
- Bonds and securitisationsStructure: notes or bonds
- Security
- GPU and associated customer cashflows
- Maturity
- 31 December 2031 or earlier on final contract fee payment
- Note principal usd m
- 2100As of 29 May 2026
Selected field only; not an independently approved claim.
Parties
Project connections
Related facilities
Similar financings
Same structure, other borrowers, closest in date.
More from IREN
Filed documents and legal terms
The documents behind this financing that are filed on SEC EDGAR, with the governing law each states. Read any document in full before relying on it; filers may redact commercial terms.
- Filed documents
- 10
- Governing law
- Washington law (1), Delaware law (1)
- Quoted in the clause and contract libraries
- 5
The CTS and any Dispute are governed by the laws of Delaware (excluding the conflicts of law rules) and the federal laws of the United States.
From the Dell purchase agreement, IE US Hardware 3 (10-Q Ex 10.4), filed with the SEC.
In-house counsel working on similar terms? Ask Randeep for a market check or see what is market.
For counsel on this deal
Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.
Sources
- IREN Microsoft GPU financing Form 8-KSource date: 29 May 2026
About this record
Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.
