| Nscale / Microsoft SOW | Microsoft's standard terms allow termination with or without cause. The SOW deletes that clause and lets either party terminate for a material breach not remedied within 60 days, or insolvency. |
| IREN / Microsoft SOW | Large parts of Microsoft's purchase order terms do not apply, including sections 7 to 17; section 14 is the termination clause. |
| IREN / Microsoft SOW | Late delivery and Exhibit A failures are carved out of material breach. |
| Sharon AI MSA | Customer may terminate for a breach not remedied in 30 days, insolvency, or a critical delivery date missed by more than 60 days where the provider is the sole cause. |
| Anthropic / Nscale GPU order | Either party may terminate for uncured material breach or the other’s insolvency, subject to any lender direct agreement. |
| Anthropic / Nscale GPU order | Anthropic may terminate if the provider stops being controlled by its parent. |
| Anthropic / Nscale GPU order | Either party may terminate if the other, or the provider’s parent, is taken over by a disqualified person. |