InfraComputeThe capital behind compute.

Analysis · Markets · 5 min read

From bitcoin to AI: how former miners are financing the switch

Bitcoin miners own what AI needs most: powered land. Three of them have now financed the switch to AI, in three different ways.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile
· Free to read · Views are personal

The short version
  1. 01TeraWulf issued US$3.2bn of 7.75% secured notes for Lake Mariner, with Google backstopping Fluidstack's lease.
  2. 02Cipher issued US$1.733bn of 7.125% secured notes for Barber Lake, with a Google backstop of Fluidstack's obligations.
  3. 03IREN finances GPUs directly: a Microsoft-backed loan at SOFR + 2.50% and a 9.0% fixed loan for non-IG customers.

A bitcoin mine is a site with a large grid connection, cooling and permits. That is the scarce input for AI compute, and several listed miners have turned their sites into AI campuses. Their financings show two distinct models.

Model one: build the data centre, lease it to a neocloud

TeraWulf and Cipher lease data centre capacity to Fluidstack, and Google stands behind Fluidstack's lease obligations. That backstop turns a lease to a young neocloud into something closer to hyperscaler credit, and it supported two large high-yield bond deals in late 2025.

  • TeraWulf's subsidiary WULF Compute issued US$3.2bn of 7.75% senior secured notes due 2030 to fund the Lake Mariner campus in New York. Security includes the borrower's assets, a lockbox account of Fluidstack's tenant entity and, until construction completes, a pledge of Google's warrants in TeraWulf.
  • Cipher issued US$1.4bn of 7.125% senior secured notes due 2030 for its Barber Lake campus in Texas, then a US$333m add-on as Fluidstack took more capacity, taking the series to US$1.733bn. Google's backstop of Fluidstack's obligations rose with it.
Figure 1

Three financing models for former miners

CompanyWhat is financedDebtCredit support
TeraWulfLake Mariner data centre leased to FluidstackUS$3.2bn 7.75% senior secured notes due 2030 (Oct 2025)Google affiliate backstop of Fluidstack lease obligations; pledge of Google's TeraWulf warrants; Fluidstack lockbox
CipherBarber Lake data centre leased to FluidstackUS$1.4bn 7.125% senior secured notes due 2030, plus US$333m add-on (Nov 2025)Google backstop of Fluidstack lease obligations; pledge of Google's Cipher warrants until initial construction completes
IRENGPUs it owns and runs for customersUS$1.545bn DDTL at SOFR + 2.50% plus up to US$2.1bn 5.96% notes; US$2.4bn at 9.0% fixedMicrosoft contract (Hardware 3); limited IREN guarantees
Sources: TeraWulf and Cipher pricing releases and SEC filings; IREN SEC filings.

Model two: own the GPUs

IREN went further and became a GPU cloud itself. Its Hardware 3 financing lends against GPUs serving Microsoft: a US$1.545bn delayed-draw loan at SOFR + 2.50% and up to US$2.1bn of 5.96% notes, rated A by Fitch. Its Mackenzie financing from Blue Owl and Pimco, at 9.0% fixed, funds GPUs in British Columbia for non-investment-grade customers.

The lessons

  • Hyperscaler credit support, through backstops or contracts, is what makes these financings work, as it did for lease-backed data centre bonds.
  • Building and leasing is a real estate credit with a long life. Owning GPUs is a shorter, operational credit, and is priced and structured differently.
  • Warrants and equity stakes held by the backstop provider are now part of some security packages.

Questions for the market

  • What does the backstop provider receive in return, and when does its support fall away?
  • How do lease-backed bonds and GPU loans share a site when both exist?
  • Which other miners have the power and permits to follow, and on what terms?

For in-house counsel

Take it to the documents

The filed wording behind this piece, for the lender’s or the borrower’s side. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. TeraWulf pricing release: investors.terawulf.com
  2. TeraWulf 10-Q, Q1 2026: sec.gov
  3. Cipher add-on pricing release: nasdaq.com
  4. Cipher 8-K: sec.gov
  5. IREN Hardware 3: SEC filing: sec.gov
  6. IREN Mackenzie: SEC filing: sec.gov

Related

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable. Firm profile. Built from public filings, company releases and rating agency reports. General information only, not legal or investment advice; views are personal and not those of any employer or client.

General information only, drawn from public documents and press reports, which are cited. It is not legal, financial or investment advice. Mention of a company or transaction does not mean the author or any firm acted on it, and nothing here is a view on any company's credit. Views are personal and are not those of any employer or client.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a GPU or data centre financing? Book 20 minutes with Randeep to compare your terms with the public deals.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.