InfraComputeThe capital behind compute.

Analysis · Structuring · 4 min read

Why the customer contract has to sit in the borrower

In a GPU loan the customer contract is the credit. If the contract sits with the parent, the lenders are lending against someone else's asset. The 2026 deals all move it into the borrower.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile
· Free to read · Views are personal

The short version
  1. 01Nscale novated its Microsoft statement of work from the group to the Ward County borrower.
  2. 02CoreWeave's DDTL 4.0 borrower holds the customer MSA and the site leases, all inside the lenders' security.
  3. 03Direct agreements with the customer give lenders notice and a chance to cure.

Neocloud sales teams sign customer contracts at group level. Lenders lend to a ring-fenced subsidiary. Before the first draw, the contract has to move from one to the other, and the way that happens matters.

Three ways to move a contract

  • Novation. The parent, the subsidiary and the customer agree that the subsidiary takes over the contract, rights and obligations together. Nscale did this with its Microsoft partner statement of work at Ward County. Novation needs the customer's consent, but it leaves the borrower as the customer's direct counterparty.
  • Signing in the borrower from the start. CoreWeave's DDTL 4.0 borrower is the counterparty to the master services agreement with its investment-grade customer, and the lenders take first-ranking security over it.
  • Security assignment. Whichever entity holds the contract assigns its rights by way of security to the lenders. Under English law this transfers the benefit, not the burden: the borrower still has to perform.
Figure 1

CoreWeave DDTL 4.0: one customer contract inside the borrower

OwnershipContract or cash flowSecurity or credit supportDirect agreement with lenders
CoreWeave, Inc.Limited guarantee onlyPledgor holding companyBorrower SPVCoreWeave Compute Acquisition Co. VIIIGPUs, customer MSA, leases, accountsFloatingSOFR + 2.25%FixedTreasury + 2.00%Collateral agentU.S. Bank TrustIG AI customerMaster services agreement(not named in the filing)DA100%100%funds drawsfirst-ranking security, incl. MSA and site leaseslimited guaranteepledgeGPU capacitymonthly feeslease assigned inlicencesguaranteeApplied DigitalEllendale lease, landlord consentOther data centre sitesLeases and colocation licencesSubsidiary guarantorsGuarantee and grant securityControlled accounts (simplified)Customer collectionsOperating costsDebt service, thenminimum liquidityCash trap if MSA breachor CoreWeave bankruptcyRelease to CoreWeave
Simplified from the DDTL 4.0 credit agreement (CoreWeave 10-Q exhibit 10.11) and the Applied Digital lease assignment. From the GPU Financing Handbook.

The direct agreement

Holding the contract is not enough on its own. If the borrower defaults under it, the customer could terminate before the lenders can act. A direct agreement between the customer and the lenders deals with that: notice of borrower defaults, a period for the lenders to cure them and the right to transfer the contract to a new operator. IREN has one with Microsoft in its Hardware 3 financing. DDTL 4.0 carries one with its customer, and Lambda's lenders have step-in rights under both customer contracts.

The same thinking extends to the site. In DDTL 4.0 the data centre leases and licences also sit in the borrower, including the Applied Digital lease at Ellendale, which was assigned in with the landlord's consent.

Questions for the next term sheet

  • Does the customer contract permit novation or assignment, and on what consent terms?
  • Will the customer sign a direct agreement, and how long is the cure period?
  • Do termination payments go to the borrower's controlled accounts?
  • Can parent-level obligations, such as service credits across a wider relationship, reach the borrower's cash?

For in-house counsel

Take it to the documents

The filed wording behind this piece, for the lender’s or the borrower’s side. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. CoreWeave DDTL 4.0: pulse2.com
  2. Nscale SEC filing, September 2026: sec.gov
  3. IREN Hardware 3: SEC filing: sec.gov
  4. Lambda Compute I: lambda.ai

Related

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable. Firm profile. Built from public filings, company releases and rating agency reports. General information only, not legal or investment advice; views are personal and not those of any employer or client.

General information only, drawn from public documents and press reports, which are cited. It is not legal, financial or investment advice. Mention of a company or transaction does not mean the author or any firm acted on it, and nothing here is a view on any company's credit. Views are personal and are not those of any employer or client.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a GPU or data centre financing? Book 20 minutes with Randeep to compare your terms with the public deals.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.