How big should a GPU debt service reserve be?

When DBRS rated Lambda's Compute I loan, it took half a notch off for one reason: the debt service reserve was lighter than the project finance norm. That puts a price on liquidity.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile
· Free to read · Views are personal

The short version
  1. 01Project finance debt service reserves are often six months of debt service.
  2. 02Aircraft ABS liquidity facilities cover several interest dates while an aircraft is repossessed and re-leased.
  3. 03The right size for a GPU reserve is the time it takes to replace a failed customer or operator.

A reserve buys time. It pays debt service while something that has gone wrong is put right. Each asset finance market sizes its reserve for the problem it expects to fix.

Figure 1

Liquidity across asset finance markets

MarketLiquidity protectionWhat it covers
Aircraft leasing and ABSLiquidity facility covering several interest datesInterest while an aircraft is repossessed and re-leased
Infrastructure project financeDebt service reserve, often six monthsA temporary outage or offtaker payment delay
Data centre ABSReserves plus a cash trapTenant default or lease non-renewal while the space is re-let
GPU loans todayDebt service reserves of varying size; DBRS cut Lambda half a notch for a light reserveNo market standard yet
Typical terms, simplified. From What Aircraft and Infrastructure Finance Teach GPU Lenders.

What problem is a GPU reserve for?

In a GPU loan the most likely problems are a customer that stops paying, an operator that fails or a cluster that loses availability. Each takes time to fix: finding a new customer for the capacity, appointing a replacement manager or replacing failed hardware. The reserve should cover that period.

The 2026 deals show different approaches. Nscale's Ward County structure has a debt service reserve alongside operating, spares and cash trap reserves. DBRS's half-notch cut on Lambda Compute I shows that rating agencies are already testing GPU reserves against the project finance norm, and pricing the difference.

Questions for the next term sheet

  • How long would it take to replace the customer on similar terms, and does the reserve cover that time?
  • Can the reserve be met with a letter of credit or parent support instead of cash?
  • Is the reserve funded at closing or built up from cash flow, and what happens in the gap?
  • Does the reserve target fall as the loan amortises?

For in-house counsel

Take it to the documents

The filed wording behind this piece, for the lender’s or the borrower’s side. Previews are open; the full text is free with InfraCompute Weekly.

Sources

  1. Lambda Compute I: lambda.ai
  2. Nscale SEC filing, September 2026: sec.gov
  3. Morningstar DBRS rating release, Lambda Compute I, 1 October 2026

Related

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable. Firm profile. Built from public filings, company releases and rating agency reports. General information only, not legal or investment advice; views are personal and not those of any employer or client.

General information only, drawn from public documents and press reports, which are cited. It is not legal, financial or investment advice. Mention of a company or transaction does not mean the author or any firm acted on it, and nothing here is a view on any company's credit. Views are personal and are not those of any employer or client.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a GPU or data centre financing? Book 20 minutes with Randeep to compare your terms with the public deals.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.