Tools  /  Regulatory tracker  /  Energy Efficiency Act: data centre duties

Regulatory tracker · Germany · Energy and efficiency

Energy Efficiency Act: data centre duties

PUE limits, reused energy shares and 100% renewable power from 2027 for German data centres of 300 kW or more.

In force Duties phase in from 2024 to 2030. New-site requirements apply to data centres starting operation from 1 July 2026.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·
Checked against the primary sources on 27 October 2026

What it does

The rule in brief

The Energieeffizienzgesetz applies to data centres with a non-redundant rated connection of 300 kW or more. Sites that started before 1 July 2026 must reach a PUE of 1.5 from 1 July 2027 and 1.3 from 1 July 2030. Sites starting from 1 July 2026 must reach a PUE of 1.2 and at least 10% reused energy (15% from July 2027 starts, 20% from July 2028 starts). Operators must cover their electricity 50% from renewables from 1 January 2024 and 100% from 1 January 2027, and publish and report information each year by 31 March.

Timeline

Key dates

DateWhat happens
1 January 202450% renewable electricity
1 July 2026New-site PUE 1.2 and reused energy duties
1 January 2027100% renewable electricity (ahead)
1 July 2027Existing sites PUE 1.5 (ahead)
1 July 2030Existing sites PUE 1.3 (ahead)

Primary sources

Read it at source

Cite as: InfraCompute regulatory tracker, “Energy Efficiency Act: data centre duties”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/de-energy-efficiency-act.

Follow alerts

Follow Energy Efficiency Act: data centre duties

New official documents and status changes. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Related

Also on the tracker

Method

Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. This entry is checked by hand at each content review. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.