The rules that move the deals.

Export controls decide where GPUs can go, screening decides who can buy them, and grid and planning rules decide when a data centre earns. Each entry gives the status, the key dates, the primary sources and what it means for a financing.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·

Regulations
30
Jurisdictions
8
Changed in the last 90 days
7
Key dates ahead
9

Recently changed

What moved

Diary

Key dates ahead

DateWhat happensWhere
2 November 2026Cyber Security and Resilience Bill
Lords third reading (scheduled)
United Kingdom
7 December 2026US outbound investment rules (31 CFR part 850)
Comments on the proposed rule due
United States
14 December 2026EU data centre energy reporting and rating scheme
Minimum standards consultation closes
European Union
1 January 2027Energy Efficiency Act: data centre duties
100% renewable electricity
Germany
1 July 2027Energy Efficiency Act: data centre duties
Existing sites PUE 1.5
Germany
17 January 2028EU Foreign Investment Screening Regulation
Fully applies
European Union
31 December 2028AgNes: reform of electricity network charges
Existing network charge rules lapse
Germany
1 July 2030Energy Efficiency Act: data centre duties
Existing sites PUE 1.3
Germany

Everything tracked

By jurisdiction

United States 12
RegulationAreaStatusLast change
AI Diffusion rule (rescinded)
The January 2025 country-tier rule was rescinded in May 2025; BIS said a replacement rule would follow.
Export controlsRescinded13 May 2025
Data Center Validated End User authorisation
Pre-approved data centres abroad can receive controlled chips without a licence for each shipment.
Export controlsIn force2 October 2024
UAE moved to Country Group A:5
Licence-free access to advanced computing items for the UAE Government and approved UAE entities.
Export controlsIn force10 July 2026
US export controls on advanced AI chips
Licences for advanced GPUs to most of the world outside close allies; China moved to case-by-case for H200-class chips.
Export controlsIn force15 January 2026
US outbound investment rules (31 CFR part 850)
Notification or prohibition of US investment in AI and semiconductor businesses in countries of concern; new rules proposed.
Investment screeningIn force26 October 2026
Executive Order 14421: foreign bulk-power system equipment
Prohibits listed transactions in foreign-produced grid equipment, including UPS and backup generators.
Grid and powerIn force9 October 2026
FERC rules for connecting large loads
DOE asked FERC to set federal rules for connecting loads over 20 MW to the transmission system, including data centres co-located with generation.
Grid and powerProposed5 December 2025
Ratepayer Protection Pledge
Seven technology companies pledged to pay for the power and grid upgrades their data centres need.
Grid and powerPolicy4 March 2026
Texas SB 6: large loads on the ERCOT grid
Interconnection standards, disclosure and curtailment rules for loads of 75 MW or more in ERCOT.
Grid and powerIn force20 June 2025
Executive Order 14318: federal permitting of data centres
Faster federal permitting and financial support for data centre projects over 100 MW or $500m capex.
Planning and permittingIn force28 July 2025
Section 232 tariff on advanced chips
25% duty on certain imported advanced chips from 15 January 2026, not applied to chips for US data centres.
Trade and tariffsIn force15 January 2026
DOJ bulk sensitive data rule (28 CFR part 202)
Restricts vendor, employment and investment agreements giving countries of concern access to bulk US data; cloud services are vendor agreements.
Data securityIn force8 April 2025
United Kingdom 8
RegulationAreaStatusLast change
National Security and Investment Act 2021
Mandatory approval before acquiring control of a UK entity in 17 sectors, including data infrastructure and computing hardware.
Investment screeningIn force15 July 2026
Cyber Security and Resilience Bill
Brings data centres of 1 MW or more (10 MW for enterprise sites) under the NIS rules, with Ofcom as regulator.
Cyber and resilienceBill in Parliament26 October 2026
Data centres designated critical national infrastructure
UK data centres were designated CNI in September 2024, alongside energy and water.
Cyber and resiliencePolicy12 September 2024
Connections reform: Gate 2 and the reordered queue
Ofgem approved NESO's reform of the connections queue: a firm date now depends on meeting readiness criteria, and the whole queue is reassessed.
Grid and powerIn force15 April 2025
Demand connections reform: Ofgem call for input
Ofgem's review of how demand, data centres above all, joins the network: firmer financial commitments first, then priority for strategic projects.
Grid and powerConsultation13 March 2026
Grid connections for strategic demand
Proposals to clear speculative demand from the queue and prioritise capacity for data centres.
Grid and powerConsultation15 April 2026
AI Growth Zones
Designated zones with grid connection priority, planning support and a proposed electricity cost discount.
Planning and permittingPolicy17 August 2026
National Planning Policy Framework (September 2026)
The new framework names data centres in plan-making and gives substantial weight to AI Growth Zone proposals.
Planning and permittingIn force29 September 2026
European Union 4
RegulationAreaStatusLast change
EU Foreign Investment Screening Regulation
Every Member State must screen foreign investment in a common set of sensitive sectors from January 2028.
Investment screeningAdopted, not yet applying17 June 2026
Critical Entities Resilience Directive
Member States identify critical entities, including digital infrastructure, which then carry physical resilience duties.
Cyber and resilienceIn force17 July 2026
NIS2 Directive
Data centre service providers are digital infrastructure entities with cyber risk and incident reporting duties.
Cyber and resilienceIn force18 October 2024
EU data centre energy reporting and rating scheme
Annual reporting for data centres of 500 kW or more; rating scheme proposed September 2026; minimum standards next.
Energy and efficiencyPartly in force21 September 2026
Germany 2
RegulationAreaStatusLast change
AgNes: reform of electricity network charges
The Bundesnetzagentur is redesigning grid charges: large consumers would pay a capacity price per kW, and the band load discount continues for existing users to 2031.
Grid and powerConsultation6 August 2026
Energy Efficiency Act: data centre duties
PUE limits, reused energy shares and 100% renewable power from 2027 for German data centres of 300 kW or more.
Energy and efficiencyIn force1 July 2026
Ireland 1
RegulationAreaStatusLast change
CRU connection policy for data centres
New data centres must bring matching dispatchable capacity and meet 80% of demand from new Irish renewables.
Grid and powerIn force20 May 2026
Netherlands 1
RegulationAreaStatusLast change
Priority rules for grid capacity in congestion areas
ACM's code decision lets grid operators give scarce capacity to priority projects first. Data centres are not a priority category.
Grid and powerIn force1 January 2026
Malaysia 1
RegulationAreaStatusLast change
Strategic Trade Permit for US-origin AI chips
Exports, transhipments and transits of high-performance US-origin AI chips need a permit.
Export controlsIn force14 July 2025
Australia 1
RegulationAreaStatusLast change
Security of Critical Infrastructure Act 2018: data storage and processing
Data centres serving government or critical infrastructure can be critical assets with registration and reporting duties.
Cyber and resilienceIn force2 April 2022

Found automatically

Latest official documents

New Federal Register documents, GOV.UK publications and bill stages for the regulations tracked here.

Follow alerts

Follow the regulatory tracker

New official documents and status changes, for one regulation or all of them. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Also tracked

Chips, power and planning

Method

Entries are written from the official text and the government, regulator and legislature pages they link to; the build rejects any other source. New Federal Register documents, GOV.UK publications and bill stages are found automatically and listed on each entry until it is next reviewed. Data centres and GPUs only. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.