Interconnection standards, disclosure and curtailment rules for loads of 75 MW or more in ERCOT.
In force Signed 20 June 2025, effective immediately. The Public Utility Commission of Texas is writing the standards.
What it does
The rule in brief
SB 6 requires the Public Utility Commission of Texas to set interconnection standards for large load customers, with a 75 MW demand threshold unless the commission sets a lower one. Large loads must disclose substantially similar requests for service elsewhere in Texas, pay a study fee of at least $100,000, and, in an emergency, may be directed to deploy on-site backup generation or curtail. ERCOT is to develop a competitively procured demand reduction service for loads of at least 75 MW.
Timeline
Key dates
| Date | What happens |
|---|---|
| 20 June 2025 | Signed by the Governor, effective immediately |
Primary sources
Read it at source
- SB 6, 89th Legislature (enrolled text) Legislature
- SB 6 bill history Legislature
Cite as: InfraCompute regulatory tracker, “Texas SB 6: large loads on the ERCOT grid”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/us-texas-sb6.
Related
Also on the tracker
US export controls on advanced AI chips
Licences for advanced GPUs to most of the world outside close allies; China moved to case-by-case for H200-class chips.
United States · Export controlsAI Diffusion rule (rescinded)
The January 2025 country-tier rule was rescinded in May 2025; BIS said a replacement rule would follow.
United States · Export controlsData Center Validated End User authorisation
Pre-approved data centres abroad can receive controlled chips without a licence for each shipment.
United States · Export controlsUAE moved to Country Group A:5
Licence-free access to advanced computing items for the UAE Government and approved UAE entities.
Method
Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. This entry is checked by hand at each content review. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.