Tools / Regulatory tracker / Demand connections reform: Ofgem call for input
Regulatory tracker · United Kingdom · Grid and power
Demand connections reform: Ofgem call for input
Ofgem's review of how demand, data centres above all, joins the network: firmer financial commitments first, then priority for strategic projects.
Consultation Call for input published 13 February 2026; responses closed 13 March 2026. Ofgem's next steps awaited.
What it does
The rule in brief
Ofgem set out three pillars for reforming demand connections: Curate, Plan and Connect. As a first phase it proposed stronger financial commitments to clear applications from non-viable data centres out of the demand queue, and mechanisms to prioritise strategic projects; a second phase would put in place a strategic plan for data centres. Ofgem records around 140 data centre projects (about 50 GW) in the demand queue, 71 of which (about 20 GW) report a final investment decision.
Timeline
Key dates
| Date | What happens |
|---|---|
| 13 February 2026 | Call for input published |
| 13 March 2026 | Responses close |
Primary sources
Read it at source
Cite as: InfraCompute regulatory tracker, “Demand connections reform: Ofgem call for input”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/gb-demand-connections-reform.
Related
Also on the tracker
Ratepayer Protection Pledge
Seven technology companies pledged to pay for the power and grid upgrades their data centres need.
United States · Grid and powerExecutive Order 14421: foreign bulk-power system equipment
Prohibits listed transactions in foreign-produced grid equipment, including UPS and backup generators.
United States · Grid and powerTexas SB 6: large loads on the ERCOT grid
Interconnection standards, disclosure and curtailment rules for loads of 75 MW or more in ERCOT.
United Kingdom · Investment screeningNational Security and Investment Act 2021
Mandatory approval before acquiring control of a UK entity in 17 sectors, including data infrastructure and computing hardware.
Method
Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. This entry is checked by hand at each content review. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.