CRU connection policy for data centres
New data centres must bring matching dispatchable capacity and meet 80% of demand from new Irish renewables.
In force CRU decision CRU/2025236 of 12 December 2025; EirGrid process (DCCOPP v3) of 20 May 2026 applies to applications of 1 MVA or more.
What it does
The rule in brief
The CRU's Large Energy Users Connection Policy applies only to data centres. New connections must come with dispatchable generation or storage, on site or nearby, matching the requested import capacity and taking part in the wholesale market; must meet at least 80% of annual demand with additional renewable generation in Ireland (not already supported by REFIT, RESS or ORESS) within a six-year glide path; and are assessed according to whether the location is constrained. EirGrid's offer process notes that judicial review proceedings have been brought against the decision.
Timeline
Key dates
| Date | What happens |
|---|---|
| 12 December 2025 | CRU decision published |
| 20 May 2026 | EirGrid DCCOPP version 3 |
Primary sources
Read it at source
- The CRU publishes its decision on new electricity connection policy for data centres (12 Dec 2025) Regulator
- EirGrid Data Centre Connection Offer Process and Policy, version 3 (20 May 2026) Regulator
Cite as: InfraCompute regulatory tracker, “CRU connection policy for data centres”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/ie-cru-data-centre-connections.
Related
Also on the tracker
Ratepayer Protection Pledge
Seven technology companies pledged to pay for the power and grid upgrades their data centres need.
United States · Grid and powerExecutive Order 14421: foreign bulk-power system equipment
Prohibits listed transactions in foreign-produced grid equipment, including UPS and backup generators.
United States · Grid and powerTexas SB 6: large loads on the ERCOT grid
Interconnection standards, disclosure and curtailment rules for loads of 75 MW or more in ERCOT.
United Kingdom · Grid and powerGrid connections for strategic demand
Proposals to clear speculative demand from the queue and prioritise capacity for data centres.
Method
Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. This entry is checked by hand at each content review. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.