Tools  /  Regulatory tracker  /  FERC rules for connecting large loads

Regulatory tracker · United States · Grid and power

FERC rules for connecting large loads

DOE asked FERC to set federal rules for connecting loads over 20 MW to the transmission system, including data centres co-located with generation.

Proposed DOE proposal of 23 October 2025 under section 403; FERC docket RM26-4-000, comments closed 21 November 2025 and reply comments 5 December 2025. Listed at the proposed rule stage in the Unified Agenda of August 2026.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·
Checked against the primary sources on 27 October 2026

What it does

The rule in brief

Using its power under section 403 of the Department of Energy Organization Act, DOE proposed that FERC assert jurisdiction over the interconnection of large loads (over 20 MW) to the interstate transmission system, including hybrid facilities that co-locate load with generation. The proposal covers standard study deposits, readiness requirements, withdrawal penalties and faster studies for loads that agree to be curtailed. DOE asked FERC to take final action by 30 April 2026.

Timeline

Key dates

DateWhat happens
23 October 2025DOE sends its proposal to FERC
27 October 2025FERC invites comments
21 November 2025Comments due
5 December 2025Reply comments due
30 April 2026Date DOE asked FERC to take final action

Primary sources

Read it at source

Cite as: InfraCompute regulatory tracker, “FERC rules for connecting large loads”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/us-ferc-large-load-interconnection.

Follow alerts

Follow FERC rules for connecting large loads

New official documents and status changes. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Related

Also on the tracker

Method

Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. New documents on the Federal Register are picked up automatically and listed here. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.