Tools  /  Regulatory tracker  /  Connections reform: Gate 2 and the reordered queue

Regulatory tracker · United Kingdom · Grid and power

Connections reform: Gate 2 and the reordered queue

Ofgem approved NESO's reform of the connections queue: a firm date now depends on meeting readiness criteria, and the whole queue is reassessed.

In force Approved by Ofgem on 15 April 2025 (the TMO4+ package, including CMP434, CMP435 and CM095).

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile ·
Checked against the primary sources on 27 October 2026

What it does

The rule in brief

The reform replaces first come, first served with two gates. Gate 1 gives an indicative offer; Gate 2 gives a confirmed queue position and connection date only to projects that meet the readiness criteria, such as secured land rights or sufficiently progressed planning, and the existing queue is reassessed against them (Gate 2 to Whole Queue). Demand projects, including data centres, are treated as needed, so for them readiness is the test. Demand connecting to the transmission network is within the reform; demand connecting to distribution networks stays on the existing process.

Timeline

Key dates

DateWhat happens
15 April 2025Ofgem approves the connections reform package

Primary sources

Read it at source

Cite as: InfraCompute regulatory tracker, “Connections reform: Gate 2 and the reordered queue”, checked 27 October 2026, https://www.infracompute.co.uk/tools/regulatory-tracker/gb-connections-reform-gate-2.

Follow alerts

Follow Connections reform: Gate 2 and the reordered queue

New official documents and status changes. One email when something changes, nothing otherwise. Confirm by email; stop with one click.

Related

Also on the tracker

Method

Each entry is written from the official text and the government, regulator or legislature pages listed above, never from secondary commentary. This entry is checked by hand at each content review. Status and dates can change after the review date, so check the source before relying on it. General information drawn from public filings. It is not legal advice on any transaction, and using this page does not create a lawyer-client relationship. Views are personal.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Book 20 minutes with Randeep.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.