Bank facilities agreement: US dollar loan facility for construction and a Thai baht working capital facility; the bank also acts as account bank for Haoyang Data Center 1 (Thailand), Up to US$590m term loan plus THB610m working capital facility, 5 November 2026.
This deal against the register
Key terms
- Borrower or issuer
- Haoyang Data Center 1 (Thailand)
- Date
- 5 November 2026Source: filing
- Structure
- Bank facilities agreement: US dollar loan facility for construction and a Thai baht working capital facility; the bank also acts as account bankOur classification
- Amount
- Up to US$590m term loan plus THB610m working capital facilitySource: filing
- Pricing
- Not on fileNot in the sources we hold
- Tenor
- USD loan facility: initial term of seven years and five months after the initial utilisation dateSource: filing
Each tag names the kind of source a term is taken from (a filing, a rating report, a company release or a news report), listed under Sources below. Our classification: a label we apply. Not on file: not in the sources we hold, so it may be undisclosed or in a document we have not yet read. Nothing is filled in by estimate. Methodology.
Recorded terms
- Lender type
- Bank loansNamed lender: A leading bank in Thailand (not named in the announcement)
- Region
- Asia PacificThailand, as the source gives itOur classification
- Tenor
- USD loan facility: initial term of seven years and five months after the initial utilisation date
- Lenders and arrangers
- A leading bank in Thailand (not named in the announcement)
- Use of proceeds
- To fund or reimburse the costs of construction and development of phase 1 (of three phases) of the data centre; THB facility for working capital
- Status
- Facilities agreement signed 5 November 2026; availability and utilisation subject to its terms and conditions
- Notes
- Borrower is Haoyang Data Center 1 (Thailand) Limited, a member of the target group that HKEX GEM-listed Zhi Sheng Group Holdings agreed to acquire on 18 September 2026. At the announcement the acquisition had not completed and the borrower was not a subsidiary of Zhi Sheng. Pricing not disclosed. The THB610m facility is shown in the amount text but not counted in the debt total.
Parties
Comparable financings
Other borrowers in the same structure family, ranked on instrument, asset, borrower, lenders, credit support, size and date. Each line says what matches and what differs.
For counsel on this deal
Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.
Construction financeFinancing a data centre build? We are happy to talk through how construction loans are being sized and taken out, and how lenders treat a lease signed before the building is finished. Talk it through
Sources
About this record
Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.
Compiled by InfraCompute · edited by Randeep Bubbra · last updated