Explainer · Deal explainer · 6 min read

DayOne's Johor facilities, explained

About US$7.3bn of five-year construction debt for data centres in Johor, Malaysia, read from the documents DayOne filed with its US listing application.

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable · Firm profile
· Free to read · Views are personal

The short version
  1. 01US$4.1bn SOFR loan and MYR 13bn Murabahah facility under one common terms agreement, five years.
  2. 02Margins of 2.20% and 2.40% fall on DayOne’s IPO; the parent stands behind completion and overruns.
  3. 03Covenants: 1.2x coverage, leverage from 7.0x to 5.0x from 2028, and debt capped at 70% of security value.

The deal in one paragraph

Four Malaysian DayOne companies, led by WG Data Hub Sdn. Bhd., borrow under a common terms agreement first signed on 15 May 2025 to build data centres in Johor. On 10 September 2026 the facilities were amended and restated and upsized: the US dollar offshore term loan grew from US$1.7bn to US$4.1bn1DayOne · Johor conventional term-loan component2025 · US$1.7bn · Development / project and the ringgit Murabahah term facility from MYR 7.5bn to MYR 13bn2DayOne · Johor green Murabahah component2025 · US$1.77bn · Development / project (about US$3.2bn), with an accordion of up to MYR 3.5bn. That is about US$7.3bn of committed debt at the exchange rate used in DayOne's F-1, which was filed with the SEC on 5 October 2026. The register records the deal at the US$7.2bn announced in October 20263DayOne Johor syndicated term loan upsize to US$7.2bnOct 2026 · US$7.2bn · Development / project.

The terms at a glance

TermWhat the filing says
BorrowersWG Data Hub Sdn. Bhd. and DayOne Data Centers Malaysia I, II and III Sdn. Bhd., cross-guaranteeing each other
FacilitiesUS$4.1bn offshore term loan; MYR 13bn Murabahah term facility; accordion up to MYR 3.5bn
TenorFive years each
PricingUS dollar loan: compounded SOFR + 2.20%, falling to 2.10% on DayOne's IPO. Ringgit facility: KLIBOR + 2.40%, falling to 2.25% on the IPO
SecurityCertain assets of and shares in the borrowers, shared pari passu with certain Malaysian bank guarantee facilities under an intercreditor deed
Parent supportA letter of undertaking from the DayOne parent to complete the projects, including equity funding, and to fund cost overruns until three months after each building is ready for service
Financial covenantsFinance service coverage at least 1.2x; net leverage from 7.00x (June 2028) stepping down to 5.00x (December 2029 on); tangible net worth floors; security margin ratio of 70%, 65% after the IPO
Change of controlMandatory repayment, after a review period, if anyone gains more than 35% of the parent's votes
Governing lawSingapore law, with SIAC arbitration
Drawn at 30 June 2026US$1,481.2m of the offshore loan and MYR 6.5bn (about US$1.6bn) of the Murabahah facility
Figure 1

Committed and drawn at 30 June 2026

DrawnCommitted, undrawn

US dollar offshore term loanUS$4.1bn committed
US$1,481.2m drawn
Ringgit Murabahah facilityMYR 13bn (about US$3.2bn) committed
MYR 6.5bn (about US$1.6bn) drawn
Amounts as stated in this piece, from DayOne's Form F-1 (5 October 2026); ringgit at the F-1 rate. Deal names link to their records. Public sources only; not a view of market terms.

Five things worth noticing

1. Two currencies, two financing traditions, one set of terms

The US dollar loan is conventional; the ringgit facility is a Murabahah, a Shariah-compliant financing built on a sale of assets at a mark-up rather than interest. The common terms agreement lets both groups of lenders share one set of covenants, events of default and security, so the two tranches move together. The agreement's own wording speaks of "profit/interest" and "Borrowings/Financings" throughout for that reason. See Murabahah.

2. Coverage is tested on project EBITDA

The finance service coverage ratio compares net cash available for finance service (EBITDA from the projects plus the finance service reserve account balance at the start of the period) with interest and principal paid under the facilities. It must be at least 1.2x over each twelve-month period, first tested for the year to 31 December 2026. We have added the clause to the clause library, beside the 1.05x to 1.40x tests in filed GPU loans.

3. Leverage is allowed to fall into place

The net leverage covenant is not tested until June 2028, when it starts at 7.00x and steps down to 5.00x by the end of 2029. That reflects a construction loan: EBITDA arrives only as halls are energised and leased, so the test waits for the buildings to earn.

4. A loan to value test, with a cure

The security margin ratio caps the debt at 70% of the security value: the value of the projects plus the money in the project accounts. It is tested within 30 days of each valuation report. If it is breached, DayOne has 14 business days to add security or prepay. The cap tightens to 65% on the IPO, with 20 business days to prepay down to it, the price of the lower margin.

5. Who the customers can be is controlled

The documents define "Whitelist Offtakers", a list of named customers (the names are redacted in the filing), with a cap on how much of the projects' IT load can be taken by customers outside the list. It is a simple way for lenders to control customer credit across a multi-tenant campus without approving every contract.

Why it matters beyond Johor

Johor has become one of the busiest data centre markets in Asia, serving Singapore's demand from across the causeway. This is one of the few filed sets of construction loan documents for a multi-building Asian data centre campus, and it shows a bank market comfortable lending billions against construction risk with a parent completion undertaking rather than a signed hyperscaler lease for every building. For sponsors elsewhere, the margins, the IPO step-downs and the delayed leverage test are useful reference points. For the wider structures, read our data centre finance guide.

See the deal record in the register.

Sources

  1. DayOne Data Centers Limited, Form F-1, "Johor Loan Facilities I" (5 October 2026): www.sec.gov
  2. Amendment and restatement deed relating to the common terms agreement, 10 September 2026, F-1 Exhibit 10.8: www.sec.gov

Related

Randeep Bubbra | Lawyer | Making the next generation of infrastructure financeable. Firm profile. General information only, drawn from public documents and press reports, which are cited. It is not legal, financial or investment advice. Mention of a company or transaction does not mean the author or any firm acted on it, and nothing here is a view on any company's credit. Views are personal and are not those of any employer or client.

General information only, drawn from public documents and press reports, which are cited. It is not legal, financial or investment advice. Mention of a company or transaction does not mean the author or any firm acted on it, and nothing here is a view on any company's credit. Views are personal and are not those of any employer or client.

For in-house counsel

Take it to the documents

The filed wording behind this piece, for the lender’s or the borrower’s side. Previews are open; the full text is free with InfraCompute Weekly.

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a GPU or data centre financing? Book 20 minutes with Randeep to compare your terms with the public deals.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.