GPU lending and US export controls: a timeline

GPU lending, on a timeline.

How GPU-secured financings in the InfraCompute register moved quarter by quarter, set beside dated US chip export-control rules, notices and elections, each with its primary source.

Updated 20 November 2026Read from the register and from primary sources

In short

The register holds 40 dated GPU-secured financings from Q4 2023 to Q4 2026. They rose each half-year from 2025 through 2026. There were 3 in H1 2025, then 7, 12 and 16 (H2 2026 runs to 27 October 2026).

Over the same period this page lists 15 dated events: US export-control rules and notices, two Nvidia disclosures and two elections. The financings and the events are shown side by side for context. The page does not say that one caused the other.

The timeline

Financings by quarter, with the events

Bars count financings in the register. Yellow dots are disclosed margins. Numbered markers are the events listed below.

GPU-secured financings per quarter, Q4 2023 to Q4 2026, with 15 numbered policy and market events00540010800Financings per quarterMargin, bp2023Q42024Q1Q2Q3Q42025Q1Q2Q3Q42026Q1Q2Q3Q4*Q4 2023: 1 GPU-secured financing in the register1Q2 2024: 1 GPU-secured financing in the register1Q1 2025: 1 GPU-secured financing in the register1Q2 2025: 2 GPU-secured financings in the register2Q3 2025: 6 GPU-secured financings in the register6Q4 2025: 1 GPU-secured financing in the register1Q1 2026: 6 GPU-secured financings in the register6Q2 2026: 6 GPU-secured financings in the register6Q3 2026: 10 GPU-secured financings in the register10Q4 2026: 6 GPU-secured financings in the register (records to 27 October 2026)6Q2 2025: margin 750 bp over the stated benchmarkQ3 2025: margin 400 bp over the stated benchmarkQ3 2025: margin 425 bp over the stated benchmarkQ1 2026: margin 225 bp over the stated benchmarkQ1 2026: margin 500 bp over the stated benchmarkQ2 2026: margin 225 bp over the stated benchmarkQ2 2026: margin 450 bp over the stated benchmarkQ3 2026: margin 250 bp over the stated benchmarkQ3 2026: margin 300 bp over the stated benchmarkQ3 2026: margin 550 bp over the stated benchmarkQ3 2026: margin 550 bp over the stated benchmark123456789101112131415GPU-secured financings per quarter, Q4 2023 to Q4 2026, one row per quarter, with 15 numbered policy and market events under their quarterFinancingsMargin, bp540010800Q4 2023Q4 2023: 1 GPU-secured financing in the register11Q1 2024Q2 2024Q2 2024: 1 GPU-secured financing in the register1Q3 2024Q4 2024234Q1 2025Q1 2025: 1 GPU-secured financing in the register15Q2 2025Q2 2025: 2 GPU-secured financings in the register2Q2 2025: margin 750 bp over the stated benchmark67Q3 2025Q3 2025: 6 GPU-secured financings in the register6Q3 2025: margin 400 bp over the stated benchmarkQ3 2025: margin 425 bp over the stated benchmark8Q4 2025Q4 2025: 1 GPU-secured financing in the register19Q1 2026Q1 2026: 6 GPU-secured financings in the register6Q1 2026: margin 225 bp over the stated benchmarkQ1 2026: margin 500 bp over the stated benchmark10Q2 2026Q2 2026: 6 GPU-secured financings in the register6Q2 2026: margin 225 bp over the stated benchmarkQ2 2026: margin 450 bp over the stated benchmarkQ3 2026Q3 2026: 10 GPU-secured financings in the register10Q3 2026: margin 250 bp over the stated benchmarkQ3 2026: margin 300 bp over the stated benchmarkQ3 2026: margin 550 bp over the stated benchmarkQ3 2026: margin 550 bp over the stated benchmark11Q4 2026*Q4 2026: 6 GPU-secured financings in the register (records to 27 October 2026)612131415
Figure 1. Bars: GPU-secured financings in the register, by the quarter of the event date. Yellow dots: the margin, in basis points over the stated benchmark, where one is disclosed (11 financings, 225 to 750 bp). Numbered markers: the events below, at their dates. The pale bar (Q4 2026*) is a part quarter. On a phone the markers sit under their quarter, in date order.
  1. 1Chip controls updated
  2. 2Validated End User for data centres
  3. 3US presidential election
  4. 4Memory and foreign direct product rules
  5. 5AI Diffusion framework published
  6. 6Nvidia H20 licence requirement
  7. 7AI Diffusion Rule rescission announced
  8. 8Affiliates rule (50% ownership)
  9. 9Affiliates rule suspended
  10. 10H200-class review case by case
  11. 11UAE moved to Country Group A:5
  12. 12US midterm elections
  13. 13Affiliates suspension extended
  14. 14Nvidia Q3 FY2027 results
  15. 15Overseas data centre rule

Counts are research coverage from public sources, not a complete market total. Register records are dated up to 27 October 2026, so Q4 2026 is a part quarter. The policy events were checked against the Federal Register, SEC EDGAR and bis.gov on 20 November 2026.

Dated events

15 dated events, each with its primary source

Rules and notices from the Federal Register and bis.gov, Nvidia filings on SEC EDGAR, and two election dates.

  1. 1

    BIS updates its advanced computing chip controls (the October 2023 rules). Published 25 October 2023; effective 17 November 2023.

    Primary source88 FR 73458
  2. 2

    BIS creates a Data Center Validated End User authorisation for pre-approved data centres.

    Primary source89 FR 80080
  3. 3

    US presidential election.

    SourceDate only
  4. 4

    BIS adds controls on high-bandwidth memory and new foreign direct product rules. Effective 2 December 2024; published 5 December.

    Primary source89 FR 96790
  5. 5

    BIS publishes the Framework for Artificial Intelligence Diffusion: worldwide licensing for advanced chips, with compliance due 15 May 2025.

    Primary source90 FR 4544
  6. 6

    The US government tells Nvidia that a licence is needed to export H20 chips to China and D:5 countries (9 April 2025). Nvidia discloses this on 15 April 2025 and expects about US$5.5bn of charges.

    Primary sourceNvidia Form 8-K
  7. 7

    Commerce announces that it is rescinding the AI Diffusion Rule before its compliance date.

    Primary sourceBIS press release
  8. 8

    BIS extends Entity List restrictions to entities at least 50% owned by listed entities (the affiliates rule). Effective 29 September 2025; published 30 September.

    Primary source90 FR 47201
  9. 9

    BIS suspends the affiliates rule for one year.

    Primary source90 FR 50857
  10. 10

    BIS moves licence review for Nvidia H200-class chips to China and Macau from a presumption of denial to case-by-case, subject to certifications.

    Primary source91 FR 1684
  11. 11

    BIS gives the UAE more favourable treatment by moving it to Country Group A:5. Effective 10 July 2026; published 14 July.

    Primary source91 FR 43034
  12. 12

    US midterm elections.

    SourceDate only
  13. 13

    BIS extends the affiliates-rule suspension to 10 January 2027.

    Primary source91 FR 70789
  14. 14

    Nvidia reports US$2.4bn of Hopper data centre shipments to China in its third quarter of fiscal 2027, and a fourth-quarter outlook that assumes no China data centre compute revenue.

    Primary sourceNvidia Form 8-K, Exhibits 99.1 and 99.2
  15. 15

    BIS issues an interim final rule restricting exports to overseas data centres that remotely supply significant compute to companies headquartered in D:5 countries or Macau, with customer due diligence for data centres, foundries and chip exporters.

    Primary source91 FR 74970
Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Request a 20-minute call.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.