Short answers, then the filings.

GPU financing is debt raised against GPUs and the customer contracts that pay for them. The usual form is a delayed draw term loan to a ring-fenced subsidiary, drawn as servers arrive and repaid from contract cash. 13 such credit agreements are on SEC EDGAR, with commitments of US$34.5bn between them. Lenders size on contract cash flow first, then test cost and recovery value.

Updated 19 November 2026Built from filed documents, rating agency releases and legislation

Not legal advice. This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.

The short answer

13

credit agreements filed on SEC EDGAR, signed July 2023 to October 2026.

US$34.5bn

in commitments across the filed agreements.

225–750bp

floating margins over SOFR on 11 GPU-secured register records.

47

GPU-secured financings in the register, by 20 borrowers.

Key figures

Key figures

What the filings show.

Every figure comes from a filed agreement, a company filing, a rating agency release or the register, with its date.

FigureWhat it isSource and date
How it works

How it works

Five parts, one ring-fenced borrower.

A GPU loan rests on a borrower that owns the GPUs, a customer that pays for them and lenders that fund each draw.

  1. SponsorThe GPU cloud. It owns the borrower and often guarantees it.
  2. BorrowerA ring-fenced subsidiary. It owns the GPUs and signs the customer contract.
  3. CustomerPays for capacity under a multi-year contract. Its credit sizes the loan.
  4. LendersFund each draw of the delayed draw term loan and take security over the GPUs, the contract and the accounts.

The sponsor owns the borrower. The borrower owns the GPUs and signs the customer contract. The customer pays the borrower, and the borrower repays the lenders.

  • 1. The borrower

    A subsidiary set up for the purpose and usually owned by the GPU cloud. It owns the GPUs and signs the customer contract, so lenders look at one ring-fenced set of assets. For example, the borrower under CoreWeave DDTL 1.0 is CoreWeave Compute Acquisition Co. II, LLC.

    SPV

  • 2. The customer contract

    A multi-year contract under which a customer pays for capacity, often a master services agreement. The lenders size the loan on its cash flow and ask the customer to acknowledge the lenders in a direct agreement.

    Master services agreement

  • 3. The delayed draw

    The commitment is not drawn on day one. Each draw funds a batch of GPUs once its conditions are met, such as an eligible customer contract, accepted equipment and equity, so lenders fund only what has arrived.

    Delayed draw term loan

  • 4. The security

    Lenders take security over the GPUs, the customer contract, the controlled accounts and the shares in the borrower, with direct agreements and often a parent guarantee.

    The GPU security package

  • 5. The repayment

    Contract cash pays interest and principal. A cash trap holds back distributions when cover falls, and a sweep can turn trapped cash into prepayment. The filed facilities trap cash at 1.10x in three filed facilities, 1.15x in one.*

    Cash trap

Read the detail

Key terms

Key terms

The terms lenders and borrowers negotiate.*

Each row is a What is market* card: the range across the filed deals it names, as at 27 October 2026.

TermWhere the filed deals sitRead

All What is market cards · The finance glossary

What has been filed

What has been filed

13 filed credit agreements, and the register behind them.

Each facility has its own summary page, with every term quoted from the agreement on SEC EDGAR.

13

credit agreements filed on SEC EDGAR, signed July 2023 to October 2026.

US$34.5bn

in commitments across the filed agreements.

Filed GPU credit agreements, newest first

13 facilities
FacilityTermsFiled agreement and record

Recent GPU-secured financings in the register

8 financings

Borrowers with a company page (financings recorded)

Open the deal library · All GPU loan summaries

UK and EU

UK and EU

Where the GPUs sit decides how security is taken.

Of the 13 filed GPU credit agreements, 1 is governed by English law, the Nscale Iceland facility signed 29 July 2026. The filed European facilities (Nscale Europe, signed 11 February 2026) are under New York law, so the law of the place where the GPUs sit still decides how security is taken and registered.

CountryForm of securityRegister, deadline and source

Read the detail

United States

United States

Security by filing, enforcement under the stay.

11 of the 13 filed GPU credit agreements are governed by New York law. The filed US deals perfect security over equipment by filing a UCC financing statement, which can be filed before the security is granted and covers later-acquired equipment. The English filing is document by document and runs to a fixed deadline.

PointThe ruleSource

Read the detail

Legal points
Where the market is split

Where the market is split

Where the filed documents and the agencies differ.

On these points two filed documents were drafted differently, and the agencies attach their own conditions. We attribute each view and give none of our own.

In the filed credit agreements

4 points

Cash trap and sweep

Newest filed

Sharon AI Project Dolomites (Filed 1 October 2026): A share of excess cash swept from customer acceptance

A different filed facility

Nscale Ward County DDTL (27 August 2026): DSCR below 1.10x traps cash; six months of it forces prepayment

Prepayment premium

Newest filed

Sharon AI Project Dolomites (Filed 1 October 2026): Make-whole on Facility B

A different filed facility

Nscale Ward County DDTL (27 August 2026): Fixed tranche: 2% then 1% to year 2; floating: 1% in year 1

Change of control

Newest filed

Sharon AI Project Dolomites (Filed 1 October 2026): Sharon AI below 50.1%: a review event, then repayment on 45 days’ notice

A different filed facility

Nscale Ward County DDTL (27 August 2026): Sponsors below 50.1% before an IPO or 35% after; an event of default

Final maturity

Newest filed

Sharon AI Project Dolomites (Filed 1 October 2026): 42 months from drawing, repaid in one bullet

A different filed facility

Nscale Ward County DDTL (27 August 2026): Earlier of the customer’s final payment and 27 February 2033

From rating agencies and the filings

3 views
Questions

Questions

Questions about GPU financing.

  • What is GPU financing?
    GPU financing is debt raised against GPUs and the customer contracts that pay for them. The usual form is a delayed draw term loan to a ring-fenced subsidiary of a GPU cloud (a neocloud), drawn as servers are delivered and repaid from the cash the customer contract produces. 13 credit agreements of this kind are on SEC EDGAR.

    GPU-backed loan · Neocloud

  • How is a GPU-backed loan sized?
    Each draw is the lower of a percentage of cost and the amount the contract cash flows support at a sizing DSCR. In the filed deals the cost limb is 90% to 95% of cost, lower before revenue starts and the sizing DSCR is 1.20x to 1.30x projected dscr to maturity. *Drawn from public sources only. Not our view of what is market.

    Advance rate · How lenders size a GPU loan

  • What does GPU financing cost?
    The register holds 11 GPU-secured financings with a disclosed floating margin: 225 to 750bp over SOFR, median 425bp, at the 22 October 2026 data cut. These are contractual margins. They exclude fees, floors, original issue discount and hedging, so they are not all-in cost.

    GPU loan margins · Financing cost calculator

  • What security do lenders take?
    Lenders take security over the GPUs, the customer contract, the controlled accounts and the shares in the borrower, with direct agreements and often a parent guarantee. The GPU security package explainer sets out each element with examples from public filings.

    The GPU security package · GPU security by country

  • What happens if the borrower or the customer fails?
    In England, for a company registered at Companies House in the UK, administration freezes enforcement against the GPUs without the administrator's consent or the court's permission (Insolvency Act 1986, Schedule B1, paragraph 43). In the United States the filing stops enforcement under the automatic stay (11 U.S.C. § 362), and there is no equivalent of section 1110, which lets aircraft financiers repossess after 60 days. The law of other jurisdictions differs. Lenders therefore build protection by contract: cash traps, sweeps, step-in rights and residual value support.

    When a borrower fails · Residual value guarantees

  • What are the cash trap and DSCR covenants?
    A cash trap holds back distributions when cover falls. The filed facilities set it at 1.10x in three filed facilities, 1.15x in one. The minimum DSCR covenant in the filed deals is 1.05x on contract cash flow, or 1.15x to 1.40x on operating income. *Drawn from public sources only. Not our view of what is market.

    Cash trap level · Where the cash stops

  • Are GPU loans fixed or floating rate?
    Both. Most filed facilities are floating over SOFR. The later facilities split a fixed rate tranche from a floating one: CoreWeave DDTL 4.0 is US$8.5bn, of which US$4.04bn fixed rate. A margin over SOFR and a fixed coupon describe different exposures, so the register does not rank them as interchangeable costs.

    Fixed or floating GPU loans

  • Are GPU loans rated?
    Some are. Lambda Compute I carries a rating of A (low) from Morningstar DBRS (October 2026), and IREN states that its Microsoft delayed draw facility is rated A by Fitch and A (low) by DBRS. None of the sponsors is itself rated investment grade, so the ratings attach to the financing.

    Rated GPU debt · GPU ABS

  • Is GPU financing the same as data centre (data center) financing?
    No. Data centre (data center) finance lends against land, power and buildings, and is repaid from rent. GPU financing lends against the servers and the customer contract for capacity. The two meet where a neocloud rents space in a data centre and borrows against the GPUs it places there.

    Data centre finance guide · GPU loan or GPU ABS

  • Should GPUs be leased or financed with a loan?
    The filed lease and the filed loans handle title, payment and the end of the term differently. The chip lease or loan page sets a filed lease beside the filed GPU credit agreements, point by point, with links to the filed wording.

    Chip lease or loan · GPU leasing guide

Primary sources

Primary sources

Where each figure and rule comes from.

Filings, rating agency releases and legislation first. Nothing on this page is new analysis, and nothing is a view on any company's credit.

Credit agreements filed on SEC EDGAR

13 sources

Rating agency releases and company filings

4 sources

Legislation

25 sources
Extras

Extras

Negotiation packs, issues lists and tools.

Previews are open. The filed wording behind the packs and the issues lists is free with the InfraCompute Weekly sign-up.

Every page in this guide

112 pages, grouped by kind.

Each page below carries a Part of: GPU financing line that links back here.

Guides (7)
Explainers and analysis (29)

Explainers and analysis

29 pages
A Cape Town Convention for Compute? Lessons for GPU LendersAnthropic's compute commitments: every counterparty in the IPO filingCash Sweep vs Cash Trap in Data Centre and GPU FinanceData Centre ABS vs GPU Loans: Why the Triggers DifferDSCR and Cash Trap Levels in GPU and Data Centre FinanceFixed-Rate Tranches in GPU Loans: Why They ArrivedGPU Financing Outside the US: Europe, Gulf, Asia-PacificGPU leasing guide: lease financing, sale and leaseback, filed dealsGPU lending and US export controls: a timelineGPU Loan Covenants: DSCR, Contract Realization Ratio, LTCGPU Loan Tenor vs Chip Life: Lessons from Aircraft FinanceGPU loan vs GPU ABS: private credit or rated debtGPU Loans: Why the Customer Contract Sits in the BorrowerGPU Spares Reserves: Compute's Maintenance ReserveGPU-Backed Loan Security Package ExplainedHow Lenders Size a GPU Loan: Advance Rates and DSCRInside Nscale's US$1.85bn Ward County GPU LoanNVIDIA in GPU Financings: Supplier, Counterparty, InvestorOn-Chain GPU Financing Explained: USD.AI FrameworksParent Guarantees in GPU Loans: Full, Limited or NonePooled vs Single-Contract GPU Loan FacilitiesRated GPU Debt: How GPU Loans Reach Investment GradeSizing the Debt Service Reserve in GPU LoansStep-In Rights and Direct Agreements in GPU and Data Centre FinanceThe GPU Lessor Model: xAI Colossus 2 Financing ExplainedWhat Anthropic's IPO filing says about its compute, leases and debtWhat Anthropic's IPO filing shows neocloud and data centre counterpartiesWho Lends to Neoclouds? GPU Lenders 2023 to 2026Why GPU Loan Margins Fell From 8.75% to 2.25%
Reports and benchmarks (5)
Research notes (8)
GPU loan summaries (14)
What is market (8)
Checklists (8)
Tools, packs and law (11)
Glossary (8)
Company pages (14)
Method

Method. Every figure is read from a filed credit agreement, a company filing, a rating agency release, legislation or the InfraCompute register, each named with its date. Each summary and quotation is read from the GPU loan summaries and the contract library, taken from the filed text. Figures are reviewed each quarter after the US filing season. Nothing on this page is a view on any company's credit. General information drawn from public filings. It is not legal advice, and using this page does not create a lawyer-client relationship.

*Drawn from public sources only. Not our view of what is market.

GPU-backed debtWorking on GPU-backed debt? We are happy to talk through how lenders are taking security over GPUs, and what happens to the chips if the customer contract ends. Request a 20-minute call

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Request a 20-minute call.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.