A A$4.25bn development financing for AirTrunk, dated 27 October 2026.

Not legal advice. This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.

This deal against the register

Key terms

Borrower or issuer
AirTrunk
Date
27 October 2026Source: company release
Structure
Green loan with margin adjustments, to fund continued development of the SYD3 campusOur classification
Amount
A$4.25bnSource: company release
Pricing
Not on fileNot in the sources we hold
Sources
1 public source below

Each tag names the kind of source a term is taken from (a filing, a rating report, a company release or a news report), listed under Sources below. Our classification: a label we apply. Not on file: not in the sources we hold, so it may be undisclosed or in a document we have not yet read. Nothing is filled in by estimate. Methodology.

How the lenders are repaid

Development credit funds land, power and construction before a data centre earns rent. It is repaid when the lease is signed and construction or permanent finance takes it out, so the lease deadline and the take-out decide the credit.

In the filed Macquarie notes to Applied Digital, the US$100m note falls due on 18 July 2026 instead of December 2027 if the hyperscaler lease is not signed by 18 April 2026, and must be repaid within 90 days of signing.

Pricing and tenor against the register*

This deal beside the other 98 development and project financings in the register. Each row says how many of them it counts. Pricing and tenor use only terms the register took from a filing or a company release; loans are compared with loans.

MeasureThis dealThe othersCounted
Margin over the benchmarkNot stated2.75% to 4.75%; median 3.125%4 with a margin from a filing or release
Who lendsbanksbanks 59%, capital markets 15%, private credit 11%85 with a lender type

Points to settle on a deal like this*

Each row gives the level in the filed development notes and data centre leases we hold. The point links to the full comparison. The filings behind these levels are governed by the law of the state where the property is (two) and New York law (one), as each states; a level is what the documents say, not a view on how a court would apply them.

PointIn the filed deals*
The lease-signing deadlineMacquarie’s US$100m note to Applied Digital: due December 2027, or 18 July 2026 if the hyperscaler lease is not signed by 18 April 2026.
Repaid when the lease is signed or the equity arrivesThe same note is repaid in full within 90 days of the lease being signed; every prepayment carries the lender’s base return.
Defaults tied to the project documentsA material breach by any party of the lease, the utility contracts or the construction contract is an event of default.
Lease delivery dates and late delivery creditsBoth filed leases give the tenant daily rent credits, rising with the delay, if halls and power are late.
Hyperscaler lease backstop (recognition agreement)90 days to find a tenant, then assume or reject
Tenant early termination and the termination feeApplied Digital lease: termination for convenience at 100% of the base rent for the rest of the term, paid before termination takes effect.

Recorded terms

Lender type
Bank loansNamed lender: Underwritten by 14 lead banks (Banco Santander, BNP Paribas, Credit...
Region
Asia PacificAustralia, as the source gives itOur classification
Lenders and arrangers
Underwritten by 14 lead banks (Banco Santander, BNP Paribas, Credit Agricole CIB, DBS Bank, Deutsche Bank, ING Bank, Mizuho Bank, MUFG Bank, National Australia Bank, Royal Bank of Canada, Societe Generale, Sumitomo Mitsui Banking Corporation, HSBC and United Overseas Bank) in a group of 32 institutions; green loan coordinators SMBC, HSBC and UOB
Use of proceeds
Continued development of the SYD3 campus in Western Sydney; completion expected by mid-2028
Status
Announced as secured, 27 October 2026
Notes
AirTrunk states this brings its total committed debt financing to about A$38.4bn globally, including more than A$19.8bn across its Australian projects. Margin savings are directed to its social impact programme. Pricing and tenor were not disclosed. An earlier library record carries the pre-close report of an A$4.3bn Australian campus loan.

Parties

Comparable financings

Other borrowers in the same structure family, ranked on instrument, asset, borrower, lenders, credit support, size and date. Each line says what matches and what differs.

Where this sits in AirTrunk’s financing path

AirTrunk’s 8 debt financings on the register, a lane for each kind of debt. This one: Construction and development debt Our classification

  • Construction and development debt
  • Bank and corporate facilities
  • Refinanced or resized, as the source records it
  1. Before thisTOK1 green loan10 Mar 2026 · Construction and development debt · ¥191.6bn
  2. After thisAirTrunk new Australian campus loan (Blackstone)2026 · Construction and development debt · A$4.3bn

See the whole path and what falls due

More from AirTrunk

All AirTrunk financings →

For counsel on this deal

Acting for a lender, borrower or sponsor on a financing like this? Start from the filed precedents. Previews are open; the full text is free with InfraCompute Weekly.

Construction financeFinancing a data centre build? We are happy to talk through how construction loans are being sized and taken out, and how lenders treat a lease signed before the building is finished. Talk it through

Sources

  1. AirTrunk: AirTrunk Secures A$4.25B Green Loan For SYD3 Western Sydney ExpansionSource date: 27 October 2026

About this record

Compiled from the sources above. Terms are as announced and may have changed since. Methodology · Send a correction.

Compiled by InfraCompute · edited by Randeep Bubbra · last updated

*Levels, ranges and positions marked with an asterisk come from the filings, company releases and register records cited on this page and in the tools it links to. They are not the author’s view of the market.

Read the structure

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Working on a data centre or GPU financing? Book 20 minutes with us to talk through how these transactions are structured and what we have seen in the market.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.