Insights · Filings read
Nvidia circular financing: what the filings show
Four links, as filed.
Circular financing is a name for a loop: a supplier funds or backs a customer, and the customer spends the money on the supplier’s products. NVIDIA’s latest filing describes four links: equity stakes, capacity purchase promises, lease guarantees of up to US$105bn for one customer, and extended payment terms. It does not use the word circular.
Updated 18 November 2026Figures read from NVIDIA’s Form 10-Q for the quarter ended 26 July 2026 and CoreWeave’s Form 10-Q for the quarter ended 30 June 2026. Last checked 18 November 2026. Data centre and data center mean the same thing here.
NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.
The short answer
US$99bn
NVIDIA’s stated equity investments in its ecosystem, with US$25bn of further commitments (26 July 2026).
US$36bn
commitments to buy cloud services from AI cloud partners, typically over six years (26 July 2026).
US$3.5bn
maximum exposure on land, power and shell guarantees for AI cloud partners (26 July 2026).
US$105bn
cap on guarantees for the SB Energy campus leased to an OpenAI affiliate (August 2026).
Key figures in the filings
Key figures
Key figures in the filings
US$51,157m
non-marketable securities on NVIDIA’s balance sheet, 26 July 2026
US$4.7bn
maximum loss exposure on equity method investments in infrastructure financiers, including future commitments
US$2.0bn
NVIDIA’s purchase of about 23 million CoreWeave Class A shares, January 2026
- US$99bn and US$25bnNVIDIA’s stated equity investments and equity investment commitments in its ecosystem26 July 2026
- US$51,157mNon-marketable securities on NVIDIA’s balance sheet (US$22,251m at 25 January 2026)26 July 2026
- US$3.3bn and US$4.7bnEquity method investments in infrastructure financiers, and the maximum loss exposure on them including future commitments26 July 2026
- US$36bnCommitments to buy cloud services from AI cloud partners, typically over six years26 July 2026
- US$3.5bnMaximum exposure on land, power and shell guarantees for AI cloud partners26 July 2026
- US$105bnCap on guarantees for the SB Energy campus leased to an OpenAI affiliateAugust 2026
- US$2.0bnNVIDIA’s purchase of about 23 million CoreWeave Class A shares at US$87.20January 2026
How the structure works
How the structure works
How the structure works
NVIDIA sells chips and systems. In its filing it also does four other things for customers and partners. We describe each from the filing. The terms vary by deal.
- 1
It takes equity.
NVIDIA holds publicly traded and private shares, and says it has committed to make more investments in AI model makers, infrastructure financiers and other private companies, subject to conditions.
- 2
It promises to buy capacity.
Under its AI cloud agreements, the cloud partner buys NVIDIA systems and NVIDIA commits to buy cloud services back. The cloud partner can stop providing the services to NVIDIA and sell them to others at better rates. NVIDIA’s commitment falls as the capacity is used by others or by NVIDIA. If the partner does not sell committed capacity to others, NVIDIA says it has agreed to buy it.
- 3
It guarantees leases.
NVIDIA gives credit support so a customer or partner can lease land, power and a data centre shell.
- 4
It allows time to pay.
Financing arrangements with some investment-grade customers include extended payment terms, which NVIDIA says affect the timing of its operating cash flow.
Key terms
Key terms
Key terms
- Equity investmentNVIDIA owns part of the customer
US$99bn
of investments and US$25bn of commitments, as NVIDIA states them.
- AI cloud agreementA two-way contract: the partner buys systems, NVIDIA buys services
US$36bn, usually six years. NVIDIA may earn a share of revenue from the capacity if criteria are met.
- Guarantee (land, power and shell)Pays the landlord if the tenant defaults
AI clouds: maximum US$3.5bn. SB Energy: capped at US$105bn, limited to defined portions of lease and power payments.
- Guarantee releaseEnds the support
The SB Energy guarantees end on events including OpenAI reaching a satisfactory credit rating, or when each lease ends.
- ReimbursementThe customer repays NVIDIA
OpenAI has agreed to reimburse and indemnify NVIDIA for certain losses. NVIDIA says it may not recover them promptly or in full.
- ExclusivityWhat NVIDIA receives for the guarantee
The SB Energy site will exclusively host NVIDIA AI infrastructure, subject to limited exceptions.
What has been filed
What has been filed
What has been filed
We list the arrangements that appear in public filings or company releases. Amounts are as stated by the source. They are commitments, caps or announced figures, not drawn balances.
- Aug 2026NVIDIA guarantees for SB Energy’s PORTS campus, Pike County, Ohio (customer: an OpenAI affiliate)Cap US$105bnAbout 4.25 GW of IT load, nine construction phases, 20-year leases. First phase expected in NVIDIA’s fiscal year 2029. NVIDIA holds an option to add credit support for about 3.8 GW more.
- Aug 2026NVIDIA minority investment in Cloverleaf InfrastructureNot disclosedCompany release, 21 August 2026.
- Jan 2026NVIDIA purchase of CoreWeave Class A sharesUS$2.0bnAbout 23 million shares at US$87.20. CoreWeave also says all GPUs in its infrastructure are NVIDIA GPUs.
- Jan 2026Apollo-led US$3.5bn capital solution for Valor Compute Infrastructure, leasing GB200 systems to a subsidiary of xAIUS$3.5bn of a US$5.4bn transactionNVIDIA “invested in VCI as an anchor Limited Partner” (Apollo release).
- Sep 2025NVIDIA and OpenAI letter of intentUp to US$100bnAt least 10 GW of NVIDIA systems. NVIDIA intends to invest “progressively as each gigawatt is deployed”. The release calls it a letter of intent.
Related register entries: NVIDIA minority equity investment, xAI Colossus 2 GPU SPV and the Valor capital solution. This table is not available as a download.
What the filing does not say
What the filing does not say
What the filing does not say
- The filing names OpenAI only in the SB Energy guarantee. It does not state an equity amount for OpenAI, Anthropic or xAI.
- It gives no list of the AI cloud partners.
- It does not state the price at which NVIDIA would buy unsold capacity.
- We could not reconcile the US$99bn to the balance sheet lines, so we quote each as stated.
- It does not set out the guarantee terms in full. NVIDIA states that its SB Energy guarantee payments are triggered by certain tenant defaults and that its guarantees are limited to defined portions of lease and power payments. This is NVIDIA’s description of its own filed contracts, not our reading of the contracts. We have not seen them.
United States
United States
United States
All the arrangements above are disclosed under US securities rules in NVIDIA’s 10-Q and in company releases. NVIDIA reports the guarantees in its commitments note and lists them as a risk. It says that if a guarantee is triggered it may assume the lease, require the landlord to find a replacement tenant, start a sale or take other remedies, and that a replacement lease may be worth less than expected.
United Kingdom and European Union
United Kingdom and European Union
United Kingdom and European Union
We found no UK or EU counterparty named in the NVIDIA filing, so this page gives no UK or EU deal. The structures can still be used in sterling or euro financings. For European GPU lenders see GPU financing outside the US.
Where the market is split
Where the market is split
Where the market is split
We attribute each view. We give none of our own.
NVIDIA
In its Form 10-Q NVIDIA says its investments and commitments enhance its growth opportunities, cultivate its ecosystem and strengthen its competitive position.
S&P Global Ratings
- Mark Habib, S&P’s head of digital infrastructure, told Reuters on 19 October 2026 that “so-called interconnected financing structures”, in which hyperscalers back large data centre projects or smaller AI firms, were something S&P was taking a “holistic” view of.
- He said S&P had no estimate of how much debt this could add.
- He also said “It is safe to assume that there is more [debt] out there that we are not seeing.” (Press report, Reuters via Business Day, because we did not find an S&P publication to cite.)
Questions about Nvidia circular financing
Questions
Questions about Nvidia circular financing
What is Nvidia circular financing?
It is a label for deals in which NVIDIA funds or backs a customer that then buys NVIDIA systems. NVIDIA’s filing describes equity stakes, capacity commitments and guarantees. It does not use the label.
How does it work in practice?
NVIDIA invests in a customer, or promises to buy the customer’s unsold capacity, or guarantees the customer’s lease. The customer uses the funding or the credit support to buy systems and build data centres.
Is it illegal or improper?
We make no such claim. We list what NVIDIA has disclosed. Anyone with a specific concern should take legal advice.
How much has Nvidia committed?
As at 26 July 2026: US$99bn of equity investments and US$25bn of commitments (NVIDIA’s words), US$36bn of AI cloud commitments, US$3.5bn of AI cloud lease guarantees and a US$105bn cap on SB Energy guarantees. The amounts overlap in purpose and are not additive. We do not give a total.
Does Nvidia lend to its customers?
The filing refers to financing arrangements, including extended payment terms for some investment-grade customers. It does not describe loans by NVIDIA to named customers.
What is the Nvidia backstop?
Under the AI cloud agreements NVIDIA says that if a partner does not sell committed capacity to others, it has agreed to buy it. The filing does not use the word backstop.
Why do lenders care?
A lender to a GPU borrower may rely on a customer contract that NVIDIA supports. See who is NVIDIA in your capital stack.
What did CoreWeave say?
In its quarter ended 30 June 2026 filing CoreWeave says NVIDIA bought about 23 million shares for US$2.0bn in January 2026 and that all the GPUs it uses today are NVIDIA GPUs.
Does this apply in the UK?
The filing names no UK or EU party.
Primary sources
Primary sources
Primary sources
- NVIDIA, Form 10-Q, quarter ended 26 July 2026
- CoreWeave, Form 10-Q, quarter ended 30 June 2026
- NVIDIA and OpenAI, release, 22 September 2025 (letter of intent)
- Apollo, release, 7 January 2026 (Valor and xAI capital solution)
- Cloverleaf Infrastructure, release, 21 August 2026
- Press (labelled): Reuters, “Hidden AI debt risks cloud tech giants’ credit outlook”, 19 October 2026, republished by Business Day
Gated extras and tools
Extras
Gated extras and tools
- GPU lender due diligence checklistFor subscribers and in-house counselThe documents and information lenders usually ask a GPU cloud for, with the customer contracts among them.
- Precedent pack: customer contracts, leases and backstopsFor subscribers and in-house counselThe filed capacity contracts, leases, guaranties and hyperscaler recognition agreements, for subscribers.
Method
Method. Every figure is read from the filings and releases linked in the text, as at the dates shown. We read each filing by searching its text for the topics above, so a statement that a filing does not say something means we did not find it. The page lists what the filings state and gives no view on whether any financing is circular. General information only, drawn from public documents, which are cited. Not legal or investment advice. Nothing here is a view on any company’s credit. Laws change and facts differ.
IMPORTANT NOTICE
Important notice
This page is general information about how these financings are commonly structured, drawn from public sources. It is not legal, financial, tax or investment advice, it is not a substitute for advice on your own circumstances, and it does not create a lawyer-client relationship with anyone. Statements of law are general summaries only. Unless a statement says otherwise, they refer to the law of England and Wales and to companies registered at Companies House in the UK; the law of other jurisdictions differs. Laws, regulations and market practice change, and this page may not reflect changes after the date shown. The facts and circumstances of every transaction differ, and the outcome in any matter depends on its documents and facts. Do not act, or refrain from acting, on the basis of this page. You should seek independent legal advice on the content of this page and on your own situation before relying on it. To the fullest extent permitted by law, we accept no responsibility or liability for any loss arising from reliance on this page.
GPU-backed debtWorking on GPU-backed debt? We are happy to talk through how lenders are taking security over GPUs, and what happens to the chips if the customer contract ends. Talk it through