Insights · Explainer
The draft data centre National Policy Statement: what it means for financing
Consent route, step by step.
The Government is consulting until 11:59pm on 8 January 2027 on a draft National Policy Statement (NPS) for data centres in England. It would guide decisions on data centres that the Secretary of State directs into the Planning Act 2008 development consent order (DCO) regime. For a lender it bears on which policy decides, what the consent allows and how long a challenge can run.
Updated 18 November 2026Consultation open until 11:59pm on 8 January 2027
NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.
The short answer
8 January 2027
Consultation closes at 11:59pm. It opened on 28 October 2026.
100 MW
of rated IT load: the indicative minimum for a section 35 direction (paragraph 24).
3
data centre section 35 directions in 2026. None is yet on the Planning Inspectorate list.
6 weeks
to file a judicial review claim against a DCO (section 118(1)).
Key dates and time limits for the data centre DCO route
Key dates
Key dates and time limits for the data centre DCO route
28 October 2026
Consultation opened; draft NPS laid before Parliament
8 January 2027
Consultation closes at 11:59pm
17 February 2027
Scrutiny period ends (paragraph 39)
7 January 2026
SI 2026/13 made; in force the next day
300 MW
Wapseys Wood, 16 March 2026: up to c.300 MW IT load
720 MW
Bedford, 15 June 2026: up to c.720 MW
240 MW
Dartford, 1 July 2026: up to 240 MW
Section 35 directions: stated maximum IT loads, not consented capacity. See the planning decisions log.
6 months
of examination (section 98(1))
3 months
to report (section 98(3))
3 months
to decide (section 107(1))
6 weeks
to challenge (section 118(1))
Deadlines can be moved (sections 98(4) and 107(3)). Acceptance takes 28 days (section 55(2)).
Data centre planning consent financing: DCO or planning permission
Two routes
Data centre planning consent financing: DCO or planning permission
Jurisdiction: England. The DCO regime for data centres applies in England only. We describe the law of England and Wales as it applies in England.
- Who decides
The Secretary of State, after an examination and a report (sections 37(2), 98 and 107).
The local planning authority first. Five recovered appeals went to the Secretary of State after an inquiry.
- How a project gets in
Only by a section 35 direction on request (sections 35 and 35ZA). Optional (draft NPS, paragraph 101).
Most projects below 100 MW (paragraphs 28 and 108), and larger ones that do not ask for a direction.
- Policy test
Once an NPS has effect, decide in accordance with it (section 104(3)), subject to section 104(4) to (8). Before then, section 105.
The draft NPS may be a material consideration (paragraphs 11 and 101).
- What the consent can include
Requirements like conditions (section 120), associated development (section 115), compulsory acquisition (section 122), removal of other consents with the relevant body’s agreement (section 150).
Permission with conditions: Slough, 10 June 2026 (paragraph 53).
- Challenge
Judicial review only, within 6 weeks (section 118(1)), with an oral permission hearing (2025 Act, section 13).
Five decision letters state a 6 weeks High Court application under section 288 of the 1990 Act.
- Timing
28 days, 6 months, 3 months and 3 months are the statutory limits. In 2025 the mean for all project types was 4.68 months to examination, 5.78 months of examination and 2.85 months to a recommendation.
Not stated in the sources we cite.
The PDF cover calls the document an Initial Proposal. gov.uk calls it the draft NPS, and so do we.
What a lender diligences on a data centre DCO
What lenders diligence
What a lender diligences on a data centre DCO
Jurisdiction: the Planning Act 2008 as it applies in England.
- 1
Which policy applies
17 February 2027
Parliamentary scrutiny ends (paragraph 39)
The draft NPS is not in effect. Scrutiny runs to 17 February 2027 (paragraph 39), then it is laid again (section 9(8)) and may be designated (section 5(4)). Until then section 105 applies, not section 104. Once designated, it can be challenged by judicial review for 6 weeks (section 13(1)).
- 2
Funding and grid evidence
Viability is assumed on submission, but evidence of funding or financial backing can be requested (paragraphs 113 and 114). A grid connection is not required at application but is at the applicant’s risk (paragraph 187).
- 3
Requirements the draft NPS points to
1.3 or better
Power Usage Effectiveness expected in the design (paragraph 140)
The Secretary of State may impose requirements on grid-dependent steps, design flexibility, financial backing and a local employment and skills plan (paragraphs 114, 120, 192 and 399). Each is a “may”. Design is expected to reach a Power Usage Effectiveness of 1.3 or better (paragraph 140). Heat reuse (paragraph 155) and water use (paragraph 419) are addressed.
- 4
Compulsory acquisition and land
5 years
to begin development unless the order says otherwise (section 154)
Compulsory acquisition needs a compelling case in the public interest (section 122(1) to (3)). The draft NPS mentions it only in passing (paragraph 13). Development must begin within 5 years of the order, unless it says otherwise (section 154).
- 5
Benefit of the order and change
The order benefits the land and persons interested in it, subject to any contrary provision (section 156). No data centre order exists, so no transfer article can be read. Changes follow Schedule 6, paragraphs 2 and 3. Section 12 of the Planning and Infrastructure Act 2025 would remove the non-material route, but was not shown as in force on 18 November 2026.
Conditions precedent for a consented data centre
Conditions precedent
Conditions precedent for a consented data centre
Jurisdiction: England. Lenders commonly ask for these before first drawdown. Schedules are negotiated deal by deal, and we do not say any named deal used this list.
Consent in force
The order as made, with its statement of reasons (section 118(1)).
Challenge period expired
No claim form filed within 6 weeks, and no claim pending (section 118(1)).
Requirements discharged
Pre-commencement requirements approved (section 120(2)), and development begun in time (section 154).
Planning obligations
Any obligations or equivalent agreements with the local authority, in agreed form.
Other consents
Environmental permits, expected to be applied for alongside (paragraph 198), and any consent the order does not displace (section 150).
Grid connection
An offer, or a clear account of its status (paragraph 187).
Judicial review risk and timing for a data centre DCO
Judicial review
Judicial review risk and timing for a data centre DCO
Jurisdiction: claims in the High Court of England and Wales, against a DCO made in England.
- The claim form must be filed within 6 weeks of publication of the order or, if later, its statement of reasons (section 118(1)).
- There is no separate statutory appeal.
- Since 18 February 2026 permission is decided at an oral hearing, and a refusal recorded as totally without merit cannot go to the Court of Appeal (2025 Act, section 13).
- From 1 October 2026 Practice Direction 54D targets a permission hearing within 3 weeks (paragraph 3.7B).
- The online text we checked on 18 November 2026 did not yet show it.
No data centre order exists to challenge. On the planning permission route, the Iver decision of 9 July 2025 has been challenged in the High Court; we have not on file the outcome (see the planning decisions log).
What to watch before 8 January 2027, and how to respond
Before the deadline
What to watch before 8 January 2027, and how to respond
No financing question
None of the 14 questions covers financing, timing or judicial review. Questions 12 and 14 are open.
The presumption
Question 8 asks about its 3 exceptions, including Green Belt (paragraph 84), where it does not apply (paragraph 349).
The threshold
Questions 9 and 10 ask about rated IT load and 100 MW (paragraph 26).
Strategic data centres
The definition is unpublished (Covenant, 28 October 2026).
Grid cost
Ofgem has proposed that data centre projects above 40 MW post a returnable commitment of about £237,500 to £712,500 per MW of requested capacity. It is a proposal; no decision has been found.
How to respond
Use the consultation page, email datacentrenps@dsit.gov.uk, or write to the Data Centre Growth Policy Team. State whether you respond as an individual or an organisation. Responses may be disclosed and analysed using artificial intelligence.
Questions about the draft data centre NPS, the DCO route and NSIP status
Questions
Questions about the draft data centre NPS, the DCO route and NSIP status
What is the draft data centre National Policy Statement?
A draft statement of national policy for data centres in England, published for consultation on 28 October 2026. Once designated it would guide decisions on data centres directed into the DCO regime (paragraphs 37 and 38).
Does a data centre need a DCO?
No. Entry is only through a section 35 direction on request, which is optional (paragraph 101). 100 MW of rated IT load is an indicative minimum (paragraph 24).
What is a data centre NSIP?
A data centre the Secretary of State has directed into the nationally significant infrastructure regime under section 35. Data centres are not listed in section 14(1) of the Planning Act 2008.
Has any data centre been consented under the DCO regime?
No. Three section 35 directions were made in 2026 (16 March 2026, 15 June 2026 and 1 July 2026). On 18 November 2026 none was on the Planning Inspectorate list, so none has been examined or decided.
Does the draft NPS say anything about funding?
Briefly. Viability is assumed on submission, but evidence of funding or financial backing may be requested (paragraphs 113 and 114).
Does the draft NPS apply to a data center in Wales, Scotland or Northern Ireland?
No. It applies to England, on land. It may be of material consideration for decisions made in Scotland and Wales.
Lender checklist for a DCO-consented data centre
Lender checklist
Lender checklist for a DCO-consented data centre
Sixteen diligence and condition precedent items, each tied to a section of the Planning Act 2008. For subscribers.
Primary sources
Primary sources
Primary sources
- Consultation page, 28 October 2026
- Draft NPS (PDF), paragraphs as cited
- Consultation questions
- SI 2026/13
- Planning Act 2008, sections 5, 9, 13
- Planning Act 2008, sections 14, 35, 35ZA, 35A
- Planning Act 2008, sections 37, 55, 98, 107
- Planning Act 2008, sections 104, 105
- Planning Act 2008, sections 115, 120, 122, 150
- Planning Act 2008, section 118
- Planning Act 2008, sections 154, 155, 156, 158
- Planning Act 2008, Schedule 6
- SI 2015/462, regulation 6
- Planning and Infrastructure Act 2025, section 13; SI 2025/1370
- Civil Procedure Rules, 196th Practice Direction Update
- Independent review of legal challenges to NSIPs, paragraph 34
- Planning Inspectorate project list
- Planning Inspectorate Management Information, July 2026
- Direction: Wapseys Wood, 16 March 2026
- Direction: Bedford, 15 June 2026
- Direction: Dartford, 1 July 2026
- Recovered appeal: Iver, 30 October 2023
- Recovered appeal: Court Lane, 6 December 2024
- Recovered appeal: Abbots Langley, 12 May 2025
- Recovered appeal: Iver, 9 July 2025
- Recovered appeal: Slough, 10 June 2026
- Data Centre Covenant, 28 October 2026
- Government response on network connections, 28 October 2026
Method
Method. Every date, section number and figure on this page is taken from the primary sources listed here. Nothing on this page is new analysis, and it gives no view on whether the draft NPS should change or on any named project.
IMPORTANT NOTICE
Important notice
This page is general information about how these financings are commonly structured, drawn from public sources. It is not legal, financial, tax or investment advice, it is not a substitute for advice on your own circumstances, and it does not create a lawyer-client relationship with anyone. Statements of law are general summaries only. Unless a statement says otherwise, they refer to the law of England and Wales and to companies registered at Companies House in the UK; the law of other jurisdictions differs. Laws, regulations and market practice change, and this page may not reflect changes after the date shown. The facts and circumstances of every transaction differ, and the outcome in any matter depends on its documents and facts. Do not act, or refrain from acting, on the basis of this page. You should seek independent legal advice on the content of this page and on your own situation before relying on it. To the fullest extent permitted by law, we accept no responsibility or liability for any loss arising from reliance on this page.
Construction financeFinancing a data centre build? We are happy to talk through how construction loans are being sized and taken out, and how lenders treat a lease signed before the building is finished. Talk it through