Data centre construction loan pricing: what the filings show

Every margin, dated.

A data centre construction loan is usually priced as a margin over SOFR, with fees on top. In the filings we read, margins run from 2.50% on short bridge loans to 5.50% and 7.75% on private credit. After the build, bonds replace the loan at fixed coupons of 6.192% to 7.875%. The margin is only part of the cost.

Updated 18 November 2026Read from the register and from filed documents

NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.

The short answer

2.50% to 2.75%

margin over SOFR on three short bridge loans for data centre builds, 2026.

4.75%

margin on the US$1.4bn Helios construction term loan, with a 2.50% SOFR floor, August 2025.

5.50% and 7.75%

margins on the New Era (Texas Critical Data Centers) Macquarie loan, April 2026.

6.192% to 7.875%

fixed bond coupons that replace the loan after the build.

Key figures

Key figures

Key figures

Figures are from the filings listed under Primary sources. A margin is added to SOFR, so it is not a total rate.

FigureWhat it isDate
  • 2.50% to 2.75%Margin over SOFR on three short bridge loans for data centre builds (Atlas Energy, TeraWulf, Applied Digital)October 2026, March 2026, May 2026
  • 4.75%Margin on the US$1.4bn Helios construction term loan, with a 2.50% SOFR floorAugust 2025
  • 5.50% and 7.75%Margins on the New Era (Texas Critical Data Centers) Macquarie loan, plus a minimum return multipleApril 2026
  • 6.192%Coupon on Hut 8’s US$3.25bn River Bend project notes, due 2042April 2026
  • 7.875% at 98.500Coupon and issue price on CleanSpark’s US$2,276.0m Sandersville notes, due 2031September 2026
How the pricing works

How the pricing works

How the pricing works

A construction lender is paid in four ways. We describe each from the filings, and the amounts change from deal to deal.

  • The margin

    A fixed spread over a benchmark. For US dollar loans the benchmark is SOFR, the secured overnight financing rate, in either its term or daily form. Nscale’s Norwegian facility uses interpolated Term SOFR for dollar loans.

  • Fees

    Upfront, undrawn (commitment) and termination fees. The Helios filing lists all three and a prepayment premium, but gives no figures.

  • Discount or premium

    Bonds can be issued below par, which raises the yield above the coupon. Lenders in private credit can take a minimum return multiple or warrants instead.

  • The shape over time

    Some margins step up to push the borrower to refinance. One steps down when the building is complete.

A lender is paid the benchmark plus a margin, plus fees, plus any discount, premium or warrantsBenchmark (SOFR)moves with the market+Marginfixed or stepped+Feesupfront, undrawn, exit+Discount, premiumor warrantspaid at issue or exit
Figure 1. What a lender is paid on a construction loan
Key terms

Key terms

Key terms

TermWhat it doesWhat the filed documents show
  • The spread over the benchmark

    Atlas Energy: 2.50%, rising by 0.50% six months after signing. Raylan Data (TeraWulf): 2.75%.

  • Margin step-up
    Raises the cost over time

    Applied Digital and SMBC: 3.50% to the six-month mark, 4.50% to one year, then 5.50%.

  • Margin step-down
    Lowers the cost once the building is done

    Nscale Kvandal South: 3.50% before completion, 3.00% for the first two years after.

  • Sets a minimum for SOFR

    Helios: 2.50%. Raylan Data: zero.

  • Paid on money not yet drawn

    Helios names undrawn fees. The Nscale filing does not state one in the part we read.

  • Minimum return multiple
    A floor on total return, whatever the term

    New Era: 1.35x on first-stage loans if no second stage is funded.

  • Warrants
    Equity as part payment

    New Era: warrants for up to 10% of the principal funded, until it reaches US$50m.

  • A bond sold below par

    Core Scientific: 99.250. CleanSpark: 98.500.

What has been filed

What has been filed

What has been filed

The table lists each document we opened, newest first. Margins are over SOFR unless stated. We give the amount the filing states, which is a commitment or an offering size, not a drawn balance.

Borrower and dealDateAmountPriceTenor and notes
  • Atlas Energy Solutions, power equipment bridge (Goldman Sachs, Barclays)Oct 2026US$424mAdjusted Term SOFR + 2.50%, plus 0.50% after six months180 days, extendable by 184 days. US$171m drawn at closing.
  • CleanSpark, Sandersville senior secured notesSep 2026US$2,276.0m7.875% fixed, issued at 98.500Due 1 October 2031. Funds the remaining build cost. Completion guarantee from CleanSpark.
  • Nscale, Kvandal South (Norway), term and VAT facilitiesJul 2026Term and revolving VATTerm: 3.50% before completion, then 3.00% to 3.75%. VAT: 2.00%.Term final maturity six years from the target completion date.
  • Applied Digital, ComputeCo 3 notes (refinanced the bridge)Jun 2026US$1.59bn7.000% fixed, issued at parDue 2031. Repaid the May 2026 bridge.
  • Applied Digital, ComputeCo 3 bridge (Goldman Sachs Bank USA agent)May 2026About US$300m†Daily Simple SOFR + 2.75%Matures 30 April 2027.
  • Hut 8, River Bend project notesApr 2026US$3.25bn6.192% fixedDue 15 November 2042. Non-recourse to Hut 8.
  • Core Scientific Finance I, senior secured notesApr 2026US$3.3bn7.750% fixed, issued at 99.250Due 2031. Repays 364-day delayed draw loans and funds a reserve.
  • New Era, Texas Critical Data Centers (Macquarie)Apr 2026Up to US$290mTerm SOFR + 5.50% (A-1, A-2) and + 7.75% (A-3, delayed draw)Matures 8 April 2029. First-priority security. Minimum return multiple and warrants.
  • TeraWulf, Raylan Data bridge (Morgan Stanley agent)Mar 2026US$500mTerm SOFR (floor zero) + 2.75%364 days. US$100m liquidity covenant.
  • Galaxy, Helios construction term loan (Deutsche Bank)Aug 2025US$1.4bnOne-month Term SOFR (2.50% floor) + 4.75%Matures 15 August 2028. Secured on all Helios assets.
  • Applied Digital, SMBC construction loan, EllendaleFeb 2025US$375mDaily Simple SOFR + 3.50%, 4.50%, then 5.50%18 months.

† The ComputeCo 3 bridge amount is from the register entry; the filing text we read states the margin, agent and maturity.

Open the register entries for the Helios loan, the Raylan Data bridge, the ComputeCo 3 bridge, the Atlas Energy bridge, the New Era loan, the River Bend notes, the Sandersville notes and Kvandal South. This table is not available as a download.

How to read the table

How to read the table

How to read the table

We do not rank deals by margin. Four things stop the margins comparing directly.

  • The tenor

    A 364-day bridge and a six-year term facility are different risks.

  • The support

    Helios has completion and limited recourse carve-out guarantees from Galaxy Digital Holdings LP. River Bend is non-recourse to Hut 8. The filings do not say how much each affects the price.

  • The extras

    New Era adds a minimum return multiple and warrants.

  • The benchmark

    The table gives the margin, not the SOFR level on the day. We do not state a total rate.

Two deals show a bridge-to-bond path. Applied Digital’s ComputeCo 3 bridge at SOFR plus 2.75% was refinanced within seven weeks of its May 2026 start by 7.000% notes. Core Scientific’s notes repaid delayed draw loans under a 364-day facility. The filings do not state the saving or cost.

United States

United States

United States

  • US construction financings in our sample are priced over SOFR.
  • Two bridges also offer a base rate alternative with a margin 1.00% lower than the SOFR margin: Raylan Data and ComputeCo 3 (1.75% against 2.75%).
  • Bank loans are private but public companies file the credit agreements or describe them in a Form 8-K or Form 10-Q on SEC EDGAR.
  • Bonds are sold privately under Rule 144A and priced in a press release.
  • Hut 8 and CleanSpark say the proceeds fund construction, reimburse earlier sponsor equity and fund a debt service reserve.
United Kingdom and European Union

United Kingdom and European Union

United Kingdom and European Union

  • We found few published construction margins for UK or EU data centres.
  • In our register the filed margins we could read are US and one Norwegian facility.
  • Nscale’s Kvandal South facility is the European example: dollar loans over interpolated Term SOFR, a margin that falls at completion, and a separate low-margin VAT facility.
  • UK and Irish deals in the register, such as the Pure DC and EdgeCore loans, do not state margins in the sources we hold.
  • A sterling or euro loan references a sterling or euro benchmark, not SOFR, so its margin does not compare with the table.
Where the market is split

Where the market is split

Where the market is split

On these points two filed deals were drafted differently. We give no view on which is better.

  • Which way the margin moves

    Applied Digital’s SMBC loan and the Atlas bridge step up over time. Nscale’s Kvandal South margin steps down after completion, from 3.50% to 3.00%.

  • The floor

    The Helios loan sets a 2.50% floor on SOFR. The Raylan Data bridge sets zero.

  • Who stands behind the build

    Galaxy Digital Holdings LP gave completion and limited recourse guarantees on Helios. Hut 8 says River Bend is non-recourse to it. CleanSpark gives a completion guarantee on the Sandersville notes.

Questions

Questions

Questions

What is data centre construction loan pricing?

It is what the lender charges for funding the build: a margin over a benchmark such as SOFR, plus fees, and sometimes a discount, a minimum return or warrants.

What margin do data centre construction loans carry?

In the filings we read, from 2.50% to 5.50% over SOFR for bank bridges and construction loans, and 5.50% to 7.75% for the New Era private credit loan.

Is the margin the interest rate?

No. Add the benchmark, which moves unless the borrower fixes it with an interest rate swap.

Why do some margins step up, and one step down?

The filings do not say. A step-up raises the cost of staying in the loan. In Nscale’s Kvandal South facility the margin falls from 3.50% to 3.00% after completion. We draw no conclusion about any one deal.

What fees come on top?

Upfront, undrawn and termination fees (Helios), a prepayment premium (Helios) and a minimum return multiple (New Era). Only some filings give the amounts.

How do bond coupons compare with loan margins?

They do not compare directly. A coupon is fixed. A margin floats over SOFR. Add the swap or SOFR level, fees and any discount first.

Do construction loans cost less with a hyperscaler tenant?

The filings we read do not link a named tenant to the margin, so we make no claim.

Does this apply to a data center in the US and a data centre in the UK?

The pricing structure is the same. The benchmark differs: SOFR for dollar loans, and a sterling or euro benchmark for sterling or euro loans. See the sections above.

Primary sources
Gated extras and tools

Extras

Gated extras and tools

Method

Method. Every figure is read from a filing or company release linked under Primary sources, or from the InfraCompute register entry for the deal. Nothing on this page is new analysis, and the page gives no view on which loan terms are better.

*Drawn from public sources only. Not our view of what is market.

Construction financeFinancing a data centre build? We are happy to talk through how construction loans are being sized and taken out, and how lenders treat a lease signed before the building is finished. Talk it through

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.

Want to run your own deal through these tools? Request a 20-minute call.

Fridays, one email. Work email only. Unsubscribe any time. Privacy.