Insights · Explainer
Data centre ABS compared with project finance and CMBS
Three routes, one asset.
A data centre can be financed three main ways. Project finance lends to a single project company against its lease, often before or during construction. A data centre ABS lends against the lease cash flow of a pool of operating buildings and can grow. A single-asset CMBS lends against a mortgage on one property or portfolio. Which one is used follows from the stage, the shape of the portfolio and the rules that apply.
Updated 17 November 2026Read from the register and from filed documents
NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.
The short answer
US$3.25bn
River Bend project notes, 6.192% fixed, due 2042, non-recourse (Hut 8, 10-Q, 2026).
113
data centre ABS issuances in the register, from master trusts.
13
data centre single-asset CMBS issuances in the register.
US$3.5bn
BX 2025-VOLT, the largest data centre CMBS of 2025 in the register (floating-rate SASB).
The three routes compared
Side by side
The three routes compared
The filed examples show the pattern, not a rule. Each row is a description of the structure, not a view on which to use.
- Who borrows
One project company for one site or campus, with a hyperscaler or other tenant.
A special purpose issuer owning many operating buildings through subsidiaries.
A single borrower owning one property or a defined portfolio.
- What secures it
The project assets, the lease and the equity in the company. River Bend: first-priority liens on substantially all issuer assets and a pledge of the issuer equity.
The leases and cash flow of the pool, under a master indenture.
A mortgage over the property, with assignment of leases and rents.
- Stage
Construction and development, then a term-out. River Bend is described by Hut 8 as a construction bond at about 95% loan to cost.
Stabilised, leased buildings. New series can fund new assets as they join the pool.
Stabilised property, or a refinancing of a take-private such as the BX issuance for QTS.
- Recourse
Limited. The River Bend notes are solely obligations of the issuer and not guaranteed by the parent, the tenant or the lease guarantor.
To the issuer and its pool. The sponsor is not the borrower.
To the borrower and the property.
- Rate
Fixed (River Bend 6.192%) or floating over SOFR for bank construction loans.
Mostly fixed. Sterling and euro series are fixed with a floating variable funding note.
Often floating with a cap and extensions, for example SWCH 2025-DATA; some fixed.
- Repayment
Interest during construction, then scheduled debt service from rent. River Bend is due November 2042.
Interest only to an anticipated repayment date about five years out, then a step-up and a sweep.
Interest only to maturity or an extension, then repayment or refinancing.
- Cash tests
DSCR covenants and lock-ups in the loan or the indenture.
DSCR cash trap (1.30x to 1.35x) and rapid amortisation (1.20x).
Debt yield and loan-to-value tests, with cash management on a breach.
- Growth
A new asset needs a new financing.
New buildings and new series under the same master trust.
Fixed collateral. New assets need a new loan.
- US securities treatment
Rule 144A notes or a bank loan.
Outside the Exchange Act ABS definition for qualifying deals since the SEC staff letter of 29 July 2026.
Exchange Act ABS. The staff letter does not cover it.
The filed examples above are in the register: Hut 8 River Bend is a project bond, the issuances on the ABS list are master trusts, and the CMBS rows on the same page are single-asset trusts.
What the filed deals show about when each is used
What drives the choice
What the filed deals show about when each is used
Stage
US$2.25bn
Vantage New Albany green construction loan, June 2025
- Construction risk is borne by project finance and bank loans.
- Vantage’s New Albany campus took a US$2.25bn green construction loan in June 2025 and DataBank’s Red Oak campus a US$2.0bn construction loan for the first three of eight buildings in April 2026.
- The operating buildings of the same platforms are financed by ABS: Vantage and DataBank are both repeat ABS issuers.
- The term-out of a construction loan is often an ABS or a term loan, as in the data centre development financing guide.
Portfolio shape
US$1.05bn
CONE 2026-DFW3, fixed-rate interest-only loan
A master trust suits many buildings and many tenants. A single-asset CMBS suits one large campus. KBRA describes CONE 2026-DFW3 as a single-borrower CMBS backed by a mortgage on two adjacent data centre assets and excess land in Allen, Texas, with a US$1.05bn fixed-rate interest-only loan. QTS has used both: a CMBS for the BX 2025-VOLT refinancing and an ABS master trust, QTS ABS II, with a run of series from August 2025 to June 2026.
Tenant credit
US$27.3bn
Meta Hyperion 6.58% senior secured bonds due 2049
A project bond is sized on one lease. The Meta Hyperion joint venture issued about US$27.3bn of 6.58% senior secured bonds due 2049 in October 2025, rated A+ by S&P as reported by the press, against a lease to Meta. An ABS pool spreads the risk across tenants and applies concentration limits.
Rules
29 July 2026
SEC staff letter on qualifying data centre securitisations
For US deals the SEC staff letter of July 2026 removed the Exchange Act ABS requirements from qualifying data centre master trusts, which narrows the regulatory cost gap with project bonds. It left single-asset CMBS inside them.
Terms that mean different things in each route
Key terms
Terms that mean different things in each route
- Coverage test
DSCR lock-up and default levels, often with a sizing DSCR.
Cash trap and rapid amortisation on the pool.
Debt yield and DSCR tests on the loan.
- Completion support
Completion support and cost overrun undertakings until completion.
Not needed for stabilised assets; new builds join the pool once eligible.
Not applicable to a stabilised property.
- Refinancing
A term-out or a mini-perm at completion.
The anticipated repayment date, then a step-up.
Maturity and extension options.
- Subordination
Mezzanine or preferred equity beside the senior debt.
Classes A-2, B and C in one series; junior interest can defer.
Classes A to E or more, by loan-to-value attachment.
- Variable funding
Delayed-draw term loans and revolvers.
A variable funding note beside the term notes.
Not usual.
How each route sits in the US and in the UK and EU
UK, EU and US
How each route sits in the US and in the UK and EU
United States
Project bonds are sold under Rule 144A, bank construction loans are private, master-trust ABS files its indentures and reports on SEC EDGAR, and CMBS trusts file under Regulation AB. The July 2026 staff letter applies to qualifying data centre securitisations where the issuer owns the data centres directly, not to single-asset CMBS.
United Kingdom and European Union
- A securitisation under the UK or EU rules is a transaction that tranches credit risk.
- Project and property finance with a single class of senior debt is often analysed under the exclusion for specialised lending exposures, where the lender has substantial control over the assets and the income they generate.
- Tranched notes backed by a pool of leases may fall inside the rules.
- The register’s sterling and euro ABS series are listed on the issuance page.
- The governing instruments are Regulation (EU) 2017/2402 and the Securitisation Regulations 2024.
Where the sources part
Where the market is split
Where the sources part
We set out the statements as the sources make them.
The regulatory line
SEC staff concluded that securities in qualifying data centre securitisations are not asset-backed securities under the Exchange Act and left single-asset CMBS outside the relief.
Source: SEC staff response, 29 July 2026.
Fixed or floating
Master-trust series in the register are mostly fixed, while the filed single-asset CMBS in the register are mostly floating (SWCH 2025-DATA, BX 2026-VLT10, CONE 2026-DFW3 in the N-PORT holdings).
Source: SEC N-PORT filings and rating agency releases.
What a bond is called
Hut 8 describes River Bend as the first investment-grade construction bond for a single-sponsor data centre.
Source: Hut 8 Form 10-Q.
Size of the order book
Press reports put the order book for the CleanSpark Sandersville notes (US$2.276bn, 7.875%) at about US$10bn and the D notes of BX 2025-VOLT at about 23 times oversubscribed.
Source: press reports, not filings.
Questions about ABS, project finance and CMBS for data centres
Questions
Questions about ABS, project finance and CMBS for data centres
Is a data centre ABS the same as a CMBS?
No. A data centre ABS is secured on the lease cash flow of a pool of buildings in a master trust. A single-asset CMBS is secured on a mortgage on one property or portfolio.
Is project finance used for operating data centres?
Mostly for new builds. A project financing lends to a single project company, often during construction, with a term-out at completion. Operating pools are usually refinanced in the ABS or CMBS market.
Which is cheaper, data centre ABS or CMBS?
The register shows coupons for each, but the deals differ in tenor, rating, rate type and collateral, so the coupons do not compare directly. We do not rank them.
Can a data centre be financed by both ABS and CMBS?
A platform can use both for different assets. QTS has a CMBS in the BX 2025-VOLT refinancing and a master trust with many series.
Does the SEC letter apply to CMBS?
No. The staff letter covers qualifying data centre securitisations where the issuer owns the data centres directly. Single-asset CMBS is still Exchange Act ABS.
How does a project bond get repaid?
From rent over the term. River Bend, for example, is due in November 2042 and has no step-up date comparable to an ABS anticipated repayment date.
Where can I see the filed deals?
On the ABS issuance page, with the single-asset CMBS listed apart, and in the deal register.
What is the difference between data center and data centre financing?
The spelling only. The structures are the same.
Primary sources
Primary sources
Primary sources
- Hut 8 Form 10-Q, June 2026 (River Bend and Beacon Point notes)
- KBRA: CONE 2026-DFW3, 20 May 2026
- SWCH Commercial Mortgage Trust 2025-DATA, SEC exhibit
- Vantage Data Centers, incremental green loan financings, 3 June 2025
- CleanSpark Form 8-K, September 2026 (Sandersville notes)
- SEC staff response on certain data center securitizations, 29 July 2026
- Regulation (EU) 2017/2402
- The Securitisation Regulations 2024 (SI 2024/102)
Gated extras and tools
Extras
Gated extras and tools
- Precedent pack: data centre securitisationFor subscribers and in-house counselThe filed indentures and supplements on SEC EDGAR, listed.
- Bond protectionsFor subscribers and in-house counselCovenants and holder protections in data centre bonds.
- Negotiation pack: development loansFor subscribers and in-house counselThe clauses that come up in a development or construction loan.
Method
Method. Every figure is read from the InfraCompute register, from a filing on SEC EDGAR, from legislation or from a rating agency or company release, linked in the text. Nothing on this page is new analysis, and the page gives no view on which structure to use.
*Drawn from public sources only. Not our view of what is market.
IMPORTANT NOTICE
Important notice
This page is general information about how these financings are commonly structured, drawn from public sources. It is not legal, financial, tax or investment advice, it is not a substitute for advice on your own circumstances, and it does not create a lawyer-client relationship with anyone. Statements of law are general summaries only. Unless a statement says otherwise, they refer to the law of England and Wales and to companies registered at Companies House in the UK; the law of other jurisdictions differs. Laws, regulations and market practice change, and this page may not reflect changes after the date shown. The facts and circumstances of every transaction differ, and the outcome in any matter depends on its documents and facts. Do not act, or refrain from acting, on the basis of this page. You should seek independent legal advice on the content of this page and on your own situation before relying on it. To the fullest extent permitted by law, we accept no responsibility or liability for any loss arising from reliance on this page.
ABS and CMBSMoving a portfolio into ABS or CMBS? We are happy to talk through how data centre securitisations treat lease terms, tenant concentration and the cash trap. Talk it through