Insights · Guide

Data centre construction and development financing

From land to rent.

A data centre is financed in stages. A development loan buys land and power and carries the project to a signed lease. A construction loan then funds the build in draws, after the equity, against certified cost, a lease and the support behind it. At completion and rent start the debt is refinanced in the bond or loan market. Each stage has its own risks and its own clauses, set out below with the filed deals.

Updated 17 November 2026Read from the register and from filed documents

NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.

The short answer

99

development and construction financings in the register as at 17 November 2026, 2022 to 2026.

US$3.25bn

River Bend project notes (Hut 8, April 2026): first-priority liens and an equity pledge, non-recourse, about 95% loan to cost.

$714,285.71

a day in delay damages, after a 14-day grace period and capped at US$60m, in the Ward County design-build contract (January 2026).

65% and 55%

advance rates on delivered and on ordered turbines in the Fermi equipment loan (February 2026).

Five stages between a plot of land and a financeable asset

How the structure works

Five stages between a plot of land and a financeable asset

We describe the structure from the filed documents. The order and the amounts change from deal to deal.

Five stages from land and power to the take-out, with the development loan and the construction loan between themLand and powersite, gridapplicationDevelopment loanbridge tothe leaseConstruction loandraws againstcertified costCompletionacceptance,rent startsTake-outABS, CMBS, termloan or bondsLease signedEquity first, then loan drawsDebt service from rent
Figure 1. The stages of a data centre financing. The development loan and the construction loan sit between the site and the take-out.
  1. 1

    Land and power

    A site needs land rights, a planning or zoning position and a path to power. These are conditions in later loans, so a lender looks at them first. For UK and Irish sites see planning decisions; for grid rules by country see power and grid. A site with its power secured is called powered land.

  2. 2

    The development loan

    US$100m

    Macquarie note, December 2025: due 18 December 2027

    • When there is no lease yet, a short loan funds the land and early works.
    • Macquarie lent Applied Digital money on this basis: a US$50m note (September 2025) and a US$100m note (December 2025).
    • The notes run for about two years but fall due within months if a lease is not signed by a set date.
    • The $100m note matures on 18 December 2027, or on 18 July 2026 if the lease is not signed by 18 April 2026.
    • The lender is repaid when the lease is signed, within 90 days, or on a preference share issue of at least US$100m.
  3. 3

    The construction loan

    95%

    loan to cost on River Bend, as Hut 8 describes it

    Once there is a lease, a construction loan to a project company funds the build. The equity goes in first. The loan then funds eligible, certified costs in draws, each subject to draw conditions such as permits, insurance and an engineer’s certificate. The loan has an availability period and a longstop date. Interest in the build period is usually funded from the loan as interest during construction.

  4. 4

    Completion and rent start

    Completion support from the sponsor, such as a cost overrun undertaking, usually falls away at completion and rent commencement. From then the lease cash flow is the credit.

  5. 5

    The take-out

    1.30x to 1.35x

    filed ABS cash trap level; rapid amortisation 1.20x

    The construction debt is repaid from a longer-term financing: a mini-perm, a term loan, a project bond or, for a stabilised portfolio, a securitisation. The annotated construction loan term sheet has lines for the ABS take-out, including the cash trap and rapid amortisation levels the refinancing assumes. See how data centre ABS works.

The terms that carry the credit, with the filed levels

Key terms

The terms that carry the credit, with the filed levels

Each line links to the clause page in the contract library, where the filed wording is checked against the document.

TermWhat it doesWhere filed documents sit
  • How much of the cost or value the lender funds. Loan to cost sets the equity needed.

    65% and 55%

    Fermi turbine loan: 65% of delivered and 55% of ordered equipment, on the lower of cost and appraised value (Fermi turbine warehouse loan). River Bend: about 95% loan to cost, as described by Hut 8.

  • The date by which a lease must be signed or the loan falls due early.

    18 April 2026

    The $100m note: due 18 July 2026 unless a lease is signed by 18 April 2026, otherwise 18 December 2027 (Macquarie $100m development note).

  • A minimum return on a development loan, as a multiple of the money lent.

    1.25 times

    The $100m note: 8% a year, paid in kind for 12 months, and a base return of 1.25 times each draw, falling to 1.06 times on repayment within four months.

  • What the contractor pays for each day of delay past a milestone.

    $714,285.71 a day

    Ward County: $714,285.71 a day after 14 days, capped at $60m, not capped for fraud, gross negligence, wilful misconduct or abandonment (Nscale Ward County design-build).

  • Money held back from each payment until the work is done.

    10%

    Ward County: 10% held until substantial completion; half released then and half 30 days after the defect period. The form of parent guarantee is marked not used.

  • What the landlord gives the tenant for late delivery of halls and power.

    Applied Digital / CoreWeave: no credit in a grace period, then rising tiers of daily rent credits; the Building 4 lease adds a tenant termination right after an outside date (Applied Digital / CoreWeave lease).

  • What the tenant pays to leave, which protects the landlord’s debt.

    100%

    Applied Digital leases: 100% of the scheduled base rent for the rest of the term. The Blackstone form lease: a scheduled fee, which the filer expects usually to start at 100% of remaining base rent (BXDC form lease).

  • A backstop from a creditworthy parent of the tenant.

    Google recognition agreements for Fluidstack leases: a right to cure, and on a default a choice between taking over the lease and paying a scheduled fee (Google recognition (TeraWulf)).

  • Sponsor undertakings to complete and to meet cost overruns.

    The annotated term sheet: a completion and cost overrun guarantee from the sponsor, falling away on completion and rent start.

  • The refinancing that repays the construction loan.

    1.30x to 1.35x

    The term sheet assumes an ABS or a term loan. Filed ABS levels: cash trap 1.30x to 1.35x, rapid amortisation 1.20x.*

*Drawn from public sources only. Not our view of what is market.

Development and construction financings in the register

What has been filed

Development and construction financings in the register

The register holds 99 development and construction financings. The table lists the largest in US dollars, euros and pounds with a stated size, newest first. The size is the amount the record states, which is a commitment or an announced amount, not a drawn balance.

FinancingDateSizeRegionWhat the record saysSource

The documents behind the clauses on this page are filed on SEC EDGAR and listed in the precedent pack for customer contracts, leases and backstops. The register also holds the Hut 8 River Bend notes and the DataBank Red Oak loan.

The US position

United States

The US position

US$3.25bn

River Bend notes, 6.192% fixed, due 2042

US$4.25bn

Beacon Point notes, 6.129% fixed, due 2042

  • US data centre construction is usually financed by a bank syndicate or by a bond.
  • Bank construction loans are floating over SOFR and are private.
  • The margins, fees and coupons in the filed deals are set out on data centre construction loan pricing.
  • Construction bonds are sold under Rule 144A: River Bend (US$3.25bn, 6.192% fixed, due 2042) and Beacon Point (US$4.25bn, 6.129% fixed, due 2042) are described in Hut 8’s Form 10-Q as solely obligations of the issuer, not guaranteed by the parent, the tenant or an affiliate.
  • The collateral in the Macquarie notes is a first-priority construction mortgage with an assignment of leases and rents, and, in River Bend, a pledge of the issuer equity.

The mechanics that vary by state are lien priority for contractors, the recording of the mortgage and what a lender must obtain from a contractor to release a payment. The filed design-build contracts show the market tools: retainage, lien waivers from the contractor and subcontractors as a condition of substantial completion, and a right for the owner to assign or pledge the contract to a lender without the contractor’s consent.

The UK and EU position

United Kingdom and European Union

The UK and EU position

In the UK and Ireland the first question is often planning and power: whether a site can be consented and connected. See planning decisions and power and grid. Lenders take English-law security by a debenture with fixed and floating charges, a legal charge over the land and a share charge over the project company, with direct agreements from the main counterparties. English law points lists the rules that change the documents.

The register has European development and construction financings, among them a facility for Pure DC in Dublin and Amsterdam (May 2026), a European refinancing for DATA4 (January 2025) and sterling and euro transactions listed in the table above. Several European platforms finance through bank clubs and development finance institutions: see ECA and DFI data centre finance.

The legal points that decide how the stages behave
Where the filed documents differ

Where the market is split

Where the filed documents differ

On these points two filed documents were drafted differently. We do not give a view on which is better.

  • The fall-away date

    The $50m note fell due on 1 February 2026 unless a 200 MW lease was signed by 31 October 2025, and otherwise ran to 9 September 2027 (Macquarie $50m development note). The $100m note fell due on 18 July 2026 unless a lease was signed by 18 April 2026 (Macquarie $100m development note).

  • The termination fee

    The Applied Digital leases state the fee as 100% of remaining base rent. The Blackstone form lease states the fee in a schedule, and the filer expects it usually to start at 100% of remaining base rent, in some leases falling over time (BXDC form lease).

  • Parent support for the builder

    The Ward County form of parent guarantee is marked not used, so retainage is the main security.

    Source: the filed design-build contract.

  • What a bond is called

    Hut 8 describes River Bend as the first investment-grade construction bond for a single-sponsor data centre, with about 95% loan to cost, while bank construction loans in the register, such as DataBank Red Oak, are floating.

    Source: Hut 8 Form 10-Q and the DataBank announcement (press).

Questions about data centre construction and development financing

Questions

Questions about data centre construction and development financing

What is data centre construction financing?

A loan to a project company that funds the build of a data centre in draws against certified costs, after the equity, repaid from a refinancing or from rent once the building is complete and leased.

What is a development loan for a data centre?

A short loan that funds land, power and early works before a tenant lease is signed. The filed Macquarie notes fall due early if a lease is not signed by a set date.

How much of the cost does a construction loan fund?

It varies. Hut 8 describes River Bend as about 95% loan to cost. The Fermi equipment loan advances 65% of delivered equipment and 55% of ordered equipment.

What is completion support?

A sponsor undertaking to complete the project and to fund cost overruns, which usually falls away at completion and rent start.

How is a data centre construction loan repaid?

By a take-out at or after completion: a term loan, a project bond or, once the assets are stabilised, a securitisation. See how data centre ABS works.

What happens if the build is late?

The contractor pays delay damages, the tenant may receive rent credits and, after an outside date, may terminate. Ward County sets $714,285.71 a day after a 14-day grace period.

Does the lender need the tenant’s parent to stand behind the lease?

Some deals use a recognition agreement from a creditworthy parent. Google signed such agreements for Fluidstack leases at TeraWulf and Cipher sites.

Is the guide the same for a data center in the US and a data centre in the UK?

The stages are the same. The security, the planning and power steps and the contractor rules differ. See the US and UK and EU sections above.

Primary sources
Gated extras and tools

Extras

Gated extras and tools

Method

Method. Every figure is read from the InfraCompute register, from a filing on SEC EDGAR, from legislation or from a rating agency or company release, linked in the text. Nothing on this page is new analysis, and the page gives no view on which structure to use.

*Drawn from public sources only. Not our view of what is market.

Construction financeFinancing a data centre build? We are happy to talk through how construction loans are being sized and taken out, and how lenders treat a lease signed before the building is finished. Talk it through

Randeep Bubbra

InfraCompute Weekly

The week in compute finance, read from the filings.

Deals, terms and the clauses behind them, for the people financing data centres, GPU clouds and the power behind them. By Randeep Bubbra.