Insights · Guide
Data centre construction and development financing
From land to rent.
A data centre is financed in stages. A development loan buys land and power and carries the project to a signed lease. A construction loan then funds the build in draws, after the equity, against certified cost, a lease and the support behind it. At completion and rent start the debt is refinanced in the bond or loan market. Each stage has its own risks and its own clauses, set out below with the filed deals.
Updated 17 November 2026Read from the register and from filed documents
NOT LEGAL ADVICE This page is general information only. Laws and regulations change and every matter differs, so take independent legal advice before acting. Read the full notice below.
The short answer
99
development and construction financings in the register as at 17 November 2026, 2022 to 2026.
US$3.25bn
River Bend project notes (Hut 8, April 2026): first-priority liens and an equity pledge, non-recourse, about 95% loan to cost.
$714,285.71
a day in delay damages, after a 14-day grace period and capped at US$60m, in the Ward County design-build contract (January 2026).
65% and 55%
advance rates on delivered and on ordered turbines in the Fermi equipment loan (February 2026).
Five stages between a plot of land and a financeable asset
How the structure works
Five stages between a plot of land and a financeable asset
We describe the structure from the filed documents. The order and the amounts change from deal to deal.
- 1
Land and power
A site needs land rights, a planning or zoning position and a path to power. These are conditions in later loans, so a lender looks at them first. For UK and Irish sites see planning decisions; for grid rules by country see power and grid. A site with its power secured is called powered land.
- 2
The development loan
US$100m
Macquarie note, December 2025: due 18 December 2027
- When there is no lease yet, a short loan funds the land and early works.
- Macquarie lent Applied Digital money on this basis: a US$50m note (September 2025) and a US$100m note (December 2025).
- The notes run for about two years but fall due within months if a lease is not signed by a set date.
- The $100m note matures on 18 December 2027, or on 18 July 2026 if the lease is not signed by 18 April 2026.
- The lender is repaid when the lease is signed, within 90 days, or on a preference share issue of at least US$100m.
- 3
The construction loan
95%
loan to cost on River Bend, as Hut 8 describes it
Once there is a lease, a construction loan to a project company funds the build. The equity goes in first. The loan then funds eligible, certified costs in draws, each subject to draw conditions such as permits, insurance and an engineer’s certificate. The loan has an availability period and a longstop date. Interest in the build period is usually funded from the loan as interest during construction.
- 4
Completion and rent start
Completion support from the sponsor, such as a cost overrun undertaking, usually falls away at completion and rent commencement. From then the lease cash flow is the credit.
- 5
The take-out
1.30x to 1.35x
filed ABS cash trap level; rapid amortisation 1.20x
The construction debt is repaid from a longer-term financing: a mini-perm, a term loan, a project bond or, for a stabilised portfolio, a securitisation. The annotated construction loan term sheet has lines for the ABS take-out, including the cash trap and rapid amortisation levels the refinancing assumes. See how data centre ABS works.
The terms that carry the credit, with the filed levels
Key terms
The terms that carry the credit, with the filed levels
Each line links to the clause page in the contract library, where the filed wording is checked against the document.
- How much of the cost or value the lender funds. Loan to cost sets the equity needed.
65% and 55%
Fermi turbine loan: 65% of delivered and 55% of ordered equipment, on the lower of cost and appraised value (Fermi turbine warehouse loan). River Bend: about 95% loan to cost, as described by Hut 8.
- The date by which a lease must be signed or the loan falls due early.
18 April 2026
The $100m note: due 18 July 2026 unless a lease is signed by 18 April 2026, otherwise 18 December 2027 (Macquarie $100m development note).
- A minimum return on a development loan, as a multiple of the money lent.
1.25 times
The $100m note: 8% a year, paid in kind for 12 months, and a base return of 1.25 times each draw, falling to 1.06 times on repayment within four months.
- What the contractor pays for each day of delay past a milestone.
$714,285.71 a day
Ward County: $714,285.71 a day after 14 days, capped at $60m, not capped for fraud, gross negligence, wilful misconduct or abandonment (Nscale Ward County design-build).
- Money held back from each payment until the work is done.
10%
Ward County: 10% held until substantial completion; half released then and half 30 days after the defect period. The form of parent guarantee is marked not used.
- What the landlord gives the tenant for late delivery of halls and power.
Applied Digital / CoreWeave: no credit in a grace period, then rising tiers of daily rent credits; the Building 4 lease adds a tenant termination right after an outside date (Applied Digital / CoreWeave lease).
- What the tenant pays to leave, which protects the landlord’s debt.
100%
Applied Digital leases: 100% of the scheduled base rent for the rest of the term. The Blackstone form lease: a scheduled fee, which the filer expects usually to start at 100% of remaining base rent (BXDC form lease).
- A backstop from a creditworthy parent of the tenant.
Google recognition agreements for Fluidstack leases: a right to cure, and on a default a choice between taking over the lease and paying a scheduled fee (Google recognition (TeraWulf)).
- Sponsor undertakings to complete and to meet cost overruns.
The annotated term sheet: a completion and cost overrun guarantee from the sponsor, falling away on completion and rent start.
- The refinancing that repays the construction loan.
1.30x to 1.35x
The term sheet assumes an ABS or a term loan. Filed ABS levels: cash trap 1.30x to 1.35x, rapid amortisation 1.20x.*
*Drawn from public sources only. Not our view of what is market.
Development and construction financings in the register
What has been filed
Development and construction financings in the register
The register holds 99 development and construction financings. The table lists the largest in US dollars, euros and pounds with a stated size, newest first. The size is the amount the record states, which is a commitment or an announced amount, not a drawn balance.
- DayOne Johor syndicated term loan upsize to US$7.2bnOct 2026US$7.2bnAsia PacificLargest data centre loan in Asia; DayOne filed for US IPO (DODC) Oct 2026Press
- CleanSpark Sandersville (Meta) senior secured notesSep 2026US$2.276bnNorth America~US$10bn order book reported; first US HY bond tied to a Meta DCSEC filing
- Vantage Data Centers North America development revolving credit facilitySep 2026US$2bnNorth AmericaInitial collateral pool of three early-stage development assetsPress
- Galaxy Digital: senior secured project notesJul 2026US$3.507bnNorth AmericaTwo buildings, 260 MW critical IT at Helios Closed July 28, 2026.Company release
- Pure DC Seinajoki (SJK01) Finland senior debtJul 2026€1.3bnEuropeSize as announced; a commitment, not a drawn balance.Press
- Meta El Paso / BlackRock JV (Project Sopaipilla) bondsJul 2026US$12.3bnNorth AmericaSize as announced; a commitment, not a drawn balance.Press
- Applied Digital 7.00% senior secured notes due 2031Jun 2026US$1.59bnNorth AmericaThird HPC building (150 MW) at Polaris Forge 1; repaid $300M bridgeSEC filing
- Hut 8 6.129% senior secured notes due 2042Jun 2026US$4.25bnNorth AmericaBeacon Point Phase 1, a 352 MW critical IT data center in Nueces County, Texas; debt service reserves Obligations solely of Beacon Point DC, not guaranteed by Hut 8, the tenant or affiliates…SEC filing
- Stargate Michigan (Related Digital, Saline Township) financingMay 2026US$14bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- Pure DC Dublin / Amsterdam facility and corporate upsizeMay 2026US$2.7bnEuropeSize as announced; a commitment, not a drawn balance.Press
- Edged financing (senior secured notes + construction loan)May 2026US$2bnNorth AmericaSize as announced; a commitment, not a drawn balance.Press
- Hut 8 River Bend 6.192% senior secured project notesApr 2026US$3.25bnNorth America245 MW River Bend data center, LouisianaSEC filing
- Core Scientific: senior secured project notesApr 2026US$3.3bnNorth AmericaCoreWeave-leased HPC sites; repaid 364-day delayed draw term loans Closed May 2026.SEC filing
- EdgeCore AS01 and AS02 Sterling construction loansApr 2026US$1.5bnNorth AmericaLimited-recourse senior secured loans on two buildingsCompany release
- DataBank Red Oak construction loanApr 2026US$2bnNorth AmericaLater upsized by US$650m to US$2.65bn total (MUFG same roles)Press
- Ares-arranged North America debt facilityFeb 2026US$2.4bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- Princeton Digital Johor syndicated loan2026US$1.2bnAsia PacificSize as announced; a commitment, not a drawn balance.Press
- TeraWulf / Fluidstack Abernathy JV HY project bondDec 2025US$1.3bnNorth AmericaSize as announced; a commitment, not a drawn balance.SEC filing
- Project Jupiter (Stack / BorderPlex, Oracle) New Mexico project loanNov 2025US$18bnNorth AmericaSept 2026: loans quoted 89-91c; Oracle force majeure / deferral notice reportedPress
- Campus construction packageNov 2025US$38bnNorth AmericaFunding indicated: SEC N-PORT filings (2026) show funds holding "Vantage Oracle TX" and "Vantage Oracle WI" loans (funded and unfunded tranches, maturity 15 Apr 2030). Texas ~US$23.25bn, Wisconsin…Press
- DataBank green construction facility upsize to US$1.6bnOct 2025US$1.6bnNot statedSize as announced; a commitment, not a drawn balance.Company release
- Meta Hyperion JV (Blue Owl) 6.58% senior secured bonds due 2049Oct 2025US$27.3bnNorth AmericaHyperion AI data center campus, Richland Parish, Louisiana Blue Owl owns ~80% of the JV, Meta 20%. Pimco bought ~$18B; BlackRock ~$3B (WSJ). Meta lease renews every four years with a residual value…Press
- Khazna Data Centers financingSep 2025US$2.62bnMiddle EastSize as announced; a commitment, not a drawn balance.Press
- Galaxy Digital: project construction senior secured term loanAug 2025US$1.4bnNorth AmericaPhase 1 conversion of Helios (Texas) for CoreWeave lease GLAS USA is agent. Galaxy contributed $350M equity.SEC filing
- Johor conventional term-loan componentJun 2025US$1.7bnAsia PacificSize as announced; a commitment, not a drawn balance.Company release
- New Albany campus green construction loanJun 2025US$2.25bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- Crusoe Abilene JV (Blue Owl, Primary Digital) phase 2 construction loanMay 2025US$7.1bnNorth AmericaPhase 2 of Abilene campus Part of $11.6B debt and equity for phase 2; ~$15B JV overall. Press-reported.Press
- Abilene phase2 JV construction loanMay 2025US$7.1bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- Bridge Data Centres senior secured bank facilityMar 2025US$2.8bnAsia PacificSize as announced; a commitment, not a drawn balance.Press
- Novva / CIM Utah AI campus construction loanMar 2025US$2bnNorth AmericaSize as announced; a commitment, not a drawn balance.Press
- Campus construction financeJan 2025US$2.3bnNorth America206 MW phase 1 at Abilene Press-reported (Bloomberg, Commercial Observer). Date approximate (January 2025).Company release
- DATA4 European refinancingJan 2025€3.3bnEuropeSize as announced; a commitment, not a drawn balance.Company release
- AdaniConneX sustainability-linked construction financingApr 2024US$1.44bnAsia PacificSize as announced; a commitment, not a drawn balance.Company release
- EdgeCore green loan (US campuses)Jan 2024US$1.9bnNorth AmericaSize as announced; a commitment, not a drawn balance.Press
- EdgeConneX US sustainability-linked financingMar 2023US$3.3bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- EdgeConneX EMEA sustainability-linked refinancingOct 2022US$2.6bnEuropeSize as announced; a commitment, not a drawn balance.Company release
- QTS green project financing (SMBC)Sep 2022US$1.28bnNorth AmericaSize as announced; a commitment, not a drawn balance.Company release
- Aligned Data Centers sustainability-linked loan upsizeMay 2022US$1.75bnNorth AmericaSize as announced; a commitment, not a drawn balance.Press
The documents behind the clauses on this page are filed on SEC EDGAR and listed in the precedent pack for customer contracts, leases and backstops. The register also holds the Hut 8 River Bend notes and the DataBank Red Oak loan.
The US position
United States
The US position
US$3.25bn
River Bend notes, 6.192% fixed, due 2042
US$4.25bn
Beacon Point notes, 6.129% fixed, due 2042
- US data centre construction is usually financed by a bank syndicate or by a bond.
- Bank construction loans are floating over SOFR and are private.
- The margins, fees and coupons in the filed deals are set out on data centre construction loan pricing.
- Construction bonds are sold under Rule 144A: River Bend (US$3.25bn, 6.192% fixed, due 2042) and Beacon Point (US$4.25bn, 6.129% fixed, due 2042) are described in Hut 8’s Form 10-Q as solely obligations of the issuer, not guaranteed by the parent, the tenant or an affiliate.
- The collateral in the Macquarie notes is a first-priority construction mortgage with an assignment of leases and rents, and, in River Bend, a pledge of the issuer equity.
The mechanics that vary by state are lien priority for contractors, the recording of the mortgage and what a lender must obtain from a contractor to release a payment. The filed design-build contracts show the market tools: retainage, lien waivers from the contractor and subcontractors as a condition of substantial completion, and a right for the owner to assign or pledge the contract to a lender without the contractor’s consent.
The UK and EU position
United Kingdom and European Union
The UK and EU position
In the UK and Ireland the first question is often planning and power: whether a site can be consented and connected. See planning decisions and power and grid. Lenders take English-law security by a debenture with fixed and floating charges, a legal charge over the land and a share charge over the project company, with direct agreements from the main counterparties. English law points lists the rules that change the documents.
The register has European development and construction financings, among them a facility for Pure DC in Dublin and Amsterdam (May 2026), a European refinancing for DATA4 (January 2025) and sterling and euro transactions listed in the table above. Several European platforms finance through bank clubs and development finance institutions: see ECA and DFI data centre finance.
The legal points that decide how the stages behave
Legal points
The legal points that decide how the stages behave
Each point is drawn from a filed document, and links to its clause page.
100%
of remaining base rent as the tenant termination fee in the filed Applied Digital leases
2%
fall in appraised value, held for 30 days, that is a default in the Fermi equipment loan unless the shortfall is paid
The lease is the credit
A termination right is only financeable if the fee repays the landlord’s debt. The filed Applied Digital leases price it at the full remaining base rent. See tenant termination and the fee.
Lender protection in the lease
A tenant subordinates its lease to the landlord’s mortgage only if the mortgagee agrees not to disturb it, through a subordination, non-disturbance and attornment agreement. Both the Applied Digital and the Blackstone form lease make it a condition. See mortgages, SNDAs and collateral assignment.
Lender rights in the construction contract
In the Ward County contract the owner may assign or pledge the contract to its tenant or any lender without the contractor’s consent and may end it for convenience, paying for work done and direct close-out costs, with no overhead or lost profit. See lender rights.
Owner-furnished equipment
Owners buy transformers, switchgear and generators directly, so the equipment is outside the contractor’s work and warranty if it is defective or damaged in shipping. See owner-furnished equipment.
Defaults tied to the project documents
The $100m development note makes a material breach by any party of a project document, or its end, an event of default, including the lease, the electric service agreement and the construction contract. See defaults tied to the project documents.
Value tests on equipment
In the Fermi equipment loan a fall of more than 2% in appraised value that leaves loan to value above target for 30 days is a default unless the shortfall is paid. See selling equipment and value tests.
Where the filed documents differ
Where the market is split
Where the filed documents differ
On these points two filed documents were drafted differently. We do not give a view on which is better.
The fall-away date
The $50m note fell due on 1 February 2026 unless a 200 MW lease was signed by 31 October 2025, and otherwise ran to 9 September 2027 (Macquarie $50m development note). The $100m note fell due on 18 July 2026 unless a lease was signed by 18 April 2026 (Macquarie $100m development note).
The termination fee
The Applied Digital leases state the fee as 100% of remaining base rent. The Blackstone form lease states the fee in a schedule, and the filer expects it usually to start at 100% of remaining base rent, in some leases falling over time (BXDC form lease).
Parent support for the builder
The Ward County form of parent guarantee is marked not used, so retainage is the main security.
Source: the filed design-build contract.
What a bond is called
Hut 8 describes River Bend as the first investment-grade construction bond for a single-sponsor data centre, with about 95% loan to cost, while bank construction loans in the register, such as DataBank Red Oak, are floating.
Source: Hut 8 Form 10-Q and the DataBank announcement (press).
Questions about data centre construction and development financing
Questions
Questions about data centre construction and development financing
What is data centre construction financing?
A loan to a project company that funds the build of a data centre in draws against certified costs, after the equity, repaid from a refinancing or from rent once the building is complete and leased.
What is a development loan for a data centre?
A short loan that funds land, power and early works before a tenant lease is signed. The filed Macquarie notes fall due early if a lease is not signed by a set date.
How much of the cost does a construction loan fund?
It varies. Hut 8 describes River Bend as about 95% loan to cost. The Fermi equipment loan advances 65% of delivered equipment and 55% of ordered equipment.
What is completion support?
A sponsor undertaking to complete the project and to fund cost overruns, which usually falls away at completion and rent start.
How is a data centre construction loan repaid?
By a take-out at or after completion: a term loan, a project bond or, once the assets are stabilised, a securitisation. See how data centre ABS works.
What happens if the build is late?
The contractor pays delay damages, the tenant may receive rent credits and, after an outside date, may terminate. Ward County sets $714,285.71 a day after a 14-day grace period.
Does the lender need the tenant’s parent to stand behind the lease?
Some deals use a recognition agreement from a creditworthy parent. Google signed such agreements for Fluidstack leases at TeraWulf and Cipher sites.
Is the guide the same for a data center in the US and a data centre in the UK?
The stages are the same. The security, the planning and power steps and the contractor rules differ. See the US and UK and EU sections above.
Primary sources
Primary sources
Primary sources
- Macquarie $100m development note, Applied Digital 8-K, Exhibit 10.1
- Macquarie $50m development note, Applied Digital 8-K, Exhibit 10.1
- Nscale Ward County design-build, KiNRG S-1/A, Exhibit 10.13
- Fermi turbine warehouse loan, Fermi 8-K, Exhibit 10.1
- Applied Digital / CoreWeave lease, Applied Digital 8-K, Exhibit 10.1
- BXDC form lease, Blackstone Digital Infrastructure Trust S-11/A, Exhibit 10.4
- Google recognition (TeraWulf), TeraWulf 8-K, Exhibit 10.1
- Hut 8 Form 10-Q, June 2026 (River Bend and Beacon Point notes)
Gated extras and tools
Extras
Gated extras and tools
- Negotiation pack: development loansFor subscribers and in-house counselEvery clause in a development or construction loan, with the filed wording for subscribers.
- Issues list: development loanFor subscribers and in-house counselPoints to raise, with where the filed deals land.
- Checklist: construction loan conditions precedentFor subscribers and in-house counselWhat a lender asks to see before the first draw.
- Annotated term sheetFor subscribers and in-house counselEach line with the filed range and where each side pushes.
Method
Method. Every figure is read from the InfraCompute register, from a filing on SEC EDGAR, from legislation or from a rating agency or company release, linked in the text. Nothing on this page is new analysis, and the page gives no view on which structure to use.
*Drawn from public sources only. Not our view of what is market.
IMPORTANT NOTICE
Important notice
This page is general information about how these financings are commonly structured, drawn from public sources. It is not legal, financial, tax or investment advice, it is not a substitute for advice on your own circumstances, and it does not create a lawyer-client relationship with anyone. Statements of law are general summaries only. Unless a statement says otherwise, they refer to the law of England and Wales and to companies registered at Companies House in the UK; the law of other jurisdictions differs. Laws, regulations and market practice change, and this page may not reflect changes after the date shown. The facts and circumstances of every transaction differ, and the outcome in any matter depends on its documents and facts. Do not act, or refrain from acting, on the basis of this page. You should seek independent legal advice on the content of this page and on your own situation before relying on it. To the fullest extent permitted by law, we accept no responsibility or liability for any loss arising from reliance on this page.